Professional Documents
Culture Documents
Cost and Time Control of Construction Projects Due To Delays in Work Progress Based On POM-QM
Cost and Time Control of Construction Projects Due To Delays in Work Progress Based On POM-QM
ISSN No:-2456-2165
Abstract:- Proper and planned construction Aspena Apartments; Odds or Time Probability.
management in managing time and costs which is a
benchmark in the success of a project. A construction I. INTRODUCTION
project, in its implementation, often finds a condition
where optimization must be carried out precisely and A construction project, in its implementation, often
quickly in meeting the time demands of a contract which finds a condition where optimization must be carried out
reflects the wishes of an owner as a provider of funds. precisely and quickly in meeting the time demands of a
Therefore, it is necessary to use the Time and Cost contract which reflects the wishes of an owner as a provider
Prediction Application for Construction Projects to be of funds. This is certainly done effectively (doing the right
able to estimate the time and costs required so that the things) and efficiently (doing the right things) by not
project can be completed on time. One method that can forgetting the quality and use of work costs. Even though an
be used is the POM-QM Based Linear Programming activity has been planned as well as possible, it still contains
method. This research is focused on knowing: uncertainty that later it will go completely according to plan.
1
Optimization of project completion costs; Risk is always present in construction projects and often
2
Optimization of project completion time; 3Opportunity causes schedule delays or cost increases (Wang & Chou,
or probability of project completion time. The data used 2003).
is from the Aspena Residence-Tangerang Apartment
Project, in terms of architectural work from the 5th Such as the research that is being examined on the
floor to the 11th floor. The results of this study are: Aspena Residence Apartment Project in Tangerang, where
1
Optimization of the acceleration time in completing this the actual progress is 72.137% of the progress planned of
project is 56 weeks (normal time 99 weeks); 2Crashing 81.309%, resulting in a minus deviation or delay in project
costs (acceleration optimization costs) obtained progress of -9.172%.
amounting to IDR 1,624,910,000; 3Opportunities or time
Therefore, a project control planning method is
probabilities with a value of Z = 3.063 and a probability
needed, one of the methods that can be used is the POM-
of 99.8%. From this research, the researcher hopes that
QM Software.The POM-QM program is a computer
this research can be useful for related parties as
program that is used to solve quantitative management
material for consideration in planning and evaluating
problems in production and operations. Ease of operation
project completion time, as well as for other new
makes POM-QM for Windows V.5.2 an alternative
projects.
application to help decision making.
Keywords:- Cost and Time Optimization; POM-QM;
Click Files
Click New and move the cursor to the crashing menu.
Click Crashing and click Ok. Input data on the number of activities
After inputting data, click the solve menu at the top left of the application window.
On the solution menu, select Chart, so you get an example of a chart diagram.
Table 3 describes the weight of work and the remaining time for each job and explains the symbols for the type of work to
be used for input in the POM-QM software.
Totals: 14.771.570.000
Table 4. Describes the normal cost of activities. The B. Develop a Crashing plan to get optimization.
financing for this project is also divided into two divisions, Optimization is done by filling in data that will be
namely material costs, and wages. In this study, for material optimized to be compared with the plan (baseline).
and wage costs, the author takes the basic unit price that Calculating work time optimization, with the addition of
already exists in the budget plan of the project being studied a target volume of work to be completed in 1 day.
(Source: Taspen Project) Calculating the number of workers required for the
optimized work item.
Calculating the additional costs incurred due to
optimization.
Under accelerated conditions, it can be seen in Table 7, that activities that are on a critical path with a slack value of zero
(0) are activities:
A1 = Waterproof Coating
D1 = ACP (alumunium composite panel)
E1 = Ceramic Floor 60x60 cm Units
F2 = Ceramic Plint HT 10/60 cm
In the next condition relaxation is carried out, this changes the working time. There are 32 activities that can be accelerated
as attached in Table 8 below:
Table 8: Calculation of forward and backward and total float (after relaxation)
Activity time Early Early Late Late
Activity slack
weeks Start Finish Start Finish
Project 93,83
A1 11.33 0.00 11.33 0.00 11.33 0.00
A2 6,67 11.33 18.00 72,33 79.00 61.00
B1 24.00 11.33 35,33 24,67 48,67 13,33
C1 16,67 35,33 52.00 57.50 74,17 22,17
C2 2.00 35,33 37,33 80.00 82.00 44,67
C3 2.83 35,33 38,17 91.00 93,83 55,67
C4 5.00 11.33 16,33 88,83 93,83 77.50
D1 43,33 11.33 54,67 11.33 54,67 0.00
E1 26,33 54,67 81.00 54,67 81.00 0.00
E2 3.00 35,33 38,33 48,67 51,67 13,33
E3 3.00 38,33 41.33 90.83 93,83 52.50
F1 4.00 38,33 42,33 89,83 93,83 51.50
F2 12.83 81.00 93,83 81.00 93,83 0.00
F3 4.00 38,33 42,33 51,67 55,67 13,33
G1 38,17 42,33 80.50 55,67 93,83 13,33
G2 1.17 38,33 39.50 73,83 75.00 35.50
G3 1.17 39.50 40,67 75.00 76,17 35.50
G4 1.17 40,67 41.83 76,17 77,33 35.50
G5 3.00 41.83 44,83 77,33 80.33 35.50
G6 11.50 44,83 56,33 80.33 91.83 35.50
G7 2.00 56,33 58,33 91.83 93,83 35.50
G8 5,67 38,33 44.00 88,17 93,83 49,83
G9 5,67 35,33 41.00 77,83 83.50 42.50
G10 3.83 41.00 44,83 83.50 87.33 42.50
G11 3.00 44,83 47,83 87.33 90.33 42.50
G12 1.17 47,83 49.00 90.33 91.50 42.50
The activity in Figure 4, which is located on the red line, is the critical path. So, by using PERT it can be determined the
sequence of work and the attachment relationship between work activities that cannot be separated. This attachment can be seen if
certain work has not been done, then the next work cannot be done.
REFERENCES