TO THE CONGRESS OF THE UNITED STATES:

I have enclosed with this message my Administration’s framework for


rebuilding infrastructure in America. Our Nation’s infrastructure is in an
unacceptable state of disrepair, which damages our country’s competitiveness
and our citizens’ quality of life. For too long, lawmakers have invested in
infrastructure inefficiently, ignored critical needs, and allowed it to
deteriorate. As a result, the United States has fallen further and further behind
other countries. It is time to give Americans the working, modern
infrastructure they deserve.

To help build a better future for all Americans, I ask the Congress to act soon on an
infrastructure bill that will: stimulate at least $1.5 trillion in new investment over
the next 10 years, shorten the process for approving projects to 2 years or less,
address unmet rural infrastructure needs, empower State and local authorities,
and train the American workforce of the future.

To develop the infrastructure framework I am transmitting today, my


Administration engaged with Governors, mayors, Federal agencies, State and local
agencies, Members of Congress, industry, and most importantly, the American
people who depend on upgraded infrastructure. The product of these efforts is a
roadmap for the Congress to draft and pass the most comprehensive
infrastructure bill in our Nation’s history. My Administration’s plan addresses
more than traditional infrastructure -- like roads, bridges, and airports -- but
addresses other needs like drinking and wastewater systems, waterways, water
resources, energy, rural infrastructure, public lands, veterans’ hospitals, and
Brownfield and Superfund sites. The reforms set forth in my plan will strengthen
the economy, make our country more competitive, reduce the costs of goods and
services for American families, and enable Americans to build their lives on top of
the best infrastructure in the world.

My Administration is committed to working with the Congress to enact a law that


will enable America’s builders to construct new, modern, and efficient
infrastructure throughout our beautiful land.

THE WHITE HOUSE,


TABLE OF CONTENTS
PART 1—FUNDING AND FINANCING INFRASTRUCTURE IMPROVEMENTS .... 3
I. INFRASTRUCTURE INCENTIVES PROGRAM ............................................................................................... 3
A. Establishment of the Incentives Program .................................................................................................... 3
B. Applicability................................................................................................................................................. 3
C. Funding ........................................................................................................................................................ 3
D. Applications and Evaluation Criteria .......................................................................................................... 4
E. Incentive Grant Awards ............................................................................................................................... 5
II. RURAL INFRASTRUCTURE PROGRAM ........................................................................................................ 5
A. Establishment of Rural Infrastructure Program .......................................................................................... 5
B. Applicability................................................................................................................................................. 6
C. Funding ........................................................................................................................................................ 6
D. Distribution of Rural Infrastructure Program Formula Funds ................................................................... 6
E. Applications and Evaluation Criteria for Rural Performance Grants......................................................... 7
F. Tribal Infrastructure .................................................................................................................................... 7
G. Territorial Infrastructure ............................................................................................................................. 7
III. TRANSFORMATIVE PROJECTS PROGRAM................................................................................................. 7
A. Establishment of Transformative Projects Program.................................................................................... 8
B. Applicability................................................................................................................................................. 8
C. Funding ....................................................................................................................................................... 8
D. Funding Tracks ............................................................................................................................................ 8
E. Technical Assistance .................................................................................................................................... 9
F. Applications and Evaluation Criteria .......................................................................................................... 9
G. Partnership Agreement and Project Milestones ...................................................................................... 9
H. Value Sharing Structure for Capital Construction Track ............................................................................ 9
I. Performance Monitoring and Oversight ...................................................................................................... 9
IV. INFRASTRUCTURE FINANCING PROGRAMS .......................................................................................... 10
A. Expand Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding and Broaden
Program Eligibility .................................................................................................................................... 10
B. Expand Railroad Rehabilitation and Improvement Financing (RRIF) and Broaden Program Eligibility 10
C. Expand Water Infrastructure Finance and Innovation Act (WIFIA) Funding and Broaden Program
Eligibility ................................................................................................................................................... 11
D. Expand Department of Agriculture Rural Utilities Service (RUS) Lending Programs Funding ............... 13
E. Create Flexibility and Broaden Eligibility to Facilitate use of Private Activity Bonds (PABs) ................ 13
V. PUBLIC LANDS INFRASTRUCTURE ............................................................................................................ 16
A. Establish Interior Maintenance Fund ........................................................................................................ 17
VI. DISPOSITION OF FEDERAL REAL PROPERTY ......................................................................................... 17
A. Codify Accelerated Depreciation for the Disposition of Non-Federal Assets with a Federal Interest Due
to Grant Receipt ......................................................................................................................................... 17
B. Streamline and Improve the Federal Real Property Disposal Process ..................................................... 17
C. Authorize Federal Divestiture of Assets that Would Be Better Managed by State, Local, or Private
Entities ....................................................................................................................................................... 19
VII. FEDERAL CAPITAL FINANCING FUND .................................................................................................... 19
A. Create Federal Capital Financing Fund ................................................................................................... 19

PART 2—ADDITIONAL PROVISIONS FOR INFRASTRUCTURE IMPROVEMENTS 20


I. TRANSPORTATION .......................................................................................................................................... 20
A. Financing ................................................................................................................................................... 20
B. Highways ................................................................................................................................................... 22
C. Transit........................................................................................................................................................ 24
D. Rail ............................................................................................................................................................ 25
E. Airports ...................................................................................................................................................... 26
II. WATER INFRASTRUCTURE .......................................................................................................................... 27
A. Financing ................................................................................................................................................... 27
B. Water Programs......................................................................................................................................... 27
C. Inland Waterways ...................................................................................................................................... 28
D. Water Infrastructure Resources ................................................................................................................. 29
III. VETERANS AFFAIRS ..................................................................................................................................... 31
A. Provide VA Real Property Flexibilities ..................................................................................................... 31
IV. LAND REVITALIZATION (BROWNFIELD/SUPERFUND REFORM) ....................................................... 32
A. Create a Superfund Revolving Loan Fund and Grant Program and Authorize National Priorities List
Sites to be Eligible for Brownfield Grants ................................................................................................. 32
B. Provide Liability Relief for States and Municipalities Acquiring Contaminated Property through Actions
as Sovereign Governments......................................................................................................................... 33
C. Provide EPA Express Settlement Authority to Enter into Administrative Agreements .............................. 33
D. Integrate Cleanup, Infrastructure and Long-term Stewardship Needs by Creating Flexibility in Funding
and Execution Requirements ..................................................................................................................... 34

PART 3—INFRASTRUCTURE PERMITTING IMPROVEMENT .......................... 35


I. FEDERAL ROLE ................................................................................................................................................ 35
A. Establishing a “One Agency, One Decision” Environmental Review Structure ....................................... 35
B. Reducing Inefficiencies in Environmental Reviews ................................................................................... 35
C. Protecting Clean Water with Greater Efficiency ....................................................................................... 42
D. Reducing Inefficiencies in the Magnuson Stevens Act ............................................................................... 44
E. Reducing Inefficiencies in Protecting Clean Air........................................................................................ 44
F. Reducing Inefficiencies in Preserving Publicly Owned Land and Historic Properties ............................. 45
II. DELEGATION TO STATES .................................................................................................................. 47
A. Expand Department of Transportation NEPA Assignment Program to Other Agencies ........................... 47
B. Allow States to Assume FHWA Responsibilities for Approval of Right-of-Way Acquisitions.................... 47
C. Broaden NEPA Assignment Program to Include Other Determinations ................................................... 48
III. PILOT PROGRAMS ......................................................................................................................................... 48
A. Performance-Based Pilot........................................................................................................................... 48
B. Negotiated Mitigation Pilot ....................................................................................................................... 49
IV. JUDICIAL REFORM ....................................................................................................................................... 49
A. Limit Injunctive Relief to Exceptional Circumstances ............................................................................... 49
B. Revise Statute of Limitations for Federal Infrastructure Permits or Decisions to 150 Days .................... 50
C. Provide Certainty in Claims on Currentness of Data in Environmental Reviews and Permits ................. 50

PART 4—WORKFORCE DEVELOPMENT ............................................................ 51


I. ACCESS TO EDUCATION AND WORKFORCE DEVELOPMENT PROGRAMS......................................... 51
A. Expand Pell Grant Eligibility to High-Quality, Short-Term Programs ..................................................... 51
B. Reform Career and Technical Education .................................................................................................. 52
C. Strengthen Ties to the Workforce for College Students ............................................................................. 52
II. EMPOWERING WORKERS ............................................................................................................................. 53
A. Reform Licensing Requirements for Individuals Seeking a Job on an Infrastructure Project ................... 53

2
PART 1—FUNDING AND FINANCING INFRASTRUCTURE IMPROVEMENTS

I. INFRASTRUCTURE INCENTIVES PROGRAM

States and localities are best equipped to understand the infrastructure investments
needs of their communities. The infrastructure incentives program, described below,
would encourage increased State, local, and private investment in infrastructure. This
program would provide for targeted Federal investments, encourage innovation,
streamline project delivery, and help transform the way infrastructure is designed,
built, and maintained.

Under this program, States and localities would receive incentives in the form of
grants. Project sponsors selected for award would execute an agreement with express
progress milestones. Federal incentive funds would be conditioned upon achieving
the milestones within identified time frames.

A. Establishment of the Incentives Program

This provision would establish the Incentives Program to maximize investment in


infrastructure. The purposes of this program would include—
 attracting significant new, non-Federal revenue streams dedicated to
infrastructure investments;
 creating significant leverage of Federal infrastructure investments;
 assuring long-term performance of capital infrastructure investments;
 modernizing infrastructure project delivery practices;
 increasing economic growth;
 spurring the development and use of new and rapidly evolving infrastructure
technology to improve cost and improve performance; and
 ensuring Federal grant recipients are accountable for achieving specific,
measurable milestones.

B. Applicability

The Incentives Program would provide support to wide-ranging classes of assets,


including the following governmental infrastructure: surface transportation and
airports, passenger rail, ports and waterways, flood control, water supply,
hydropower, water resources, drinking water facilities, wastewater facilities,
stormwater facilities, and Brownfield and Superfund sites.

C. Funding

 $100 billion would be made available for the Incentives Program. The funds
would be divided in specific amounts to be administered by the United States
Department of Transportation (DOT), United States Army Corps of Engineers
(USACE), and Environmental Protection Agency (EPA).

3
 Other Federal agencies seeking to incentivize eligible projects within their areas
of jurisdiction could petition DOT, USACE, or EPA to transfer Incentives
Program funds to be used consistent with the requirements under the program.
 A percentage of the Incentives Program funds would be set aside for temporary
administrative expenses necessary to administer the program.

D. Applications and Evaluation Criteria

 Each lead Federal agency would solicit applications as soon as practicable after
enactment of the Incentives Program and every six months thereafter.
 Each lead Federal agency would determine the content, format, and timing of
applications and would make incentive awards. Applications also would
include information on each of the evaluation criteria.
 The evaluation criteria would be—
o the dollar value of the project or program of projects (weighted at 10
percent);
o evidence supporting how the applicant will secure and commit new, non-
Federal revenue to create sustainable, long-term funding for infrastructure
investments (weighted at 50 percent);
o evidence supporting how the applicant will secure and commit new, non-
Federal revenue for operations, maintenance and rehabilitation (weighted
at 20 percent);
o updates to procurement policies and project delivery approaches to improve
efficiency in project delivery and operations (weighted at 10 percent);
o plans to incorporate new and evolving technologies (weighted at 5 percent);
and
o evidence supporting how the project will spur economic and social returns
on investment (weighted at 5 percent).
 Each lead Federal agency would calculate each application score by multiplying
the weighted score from the evaluation criteria by the percentage of non-
Federal revenues (out of total revenues) that would be used to fund the project
or program of projects.
 To ensure that applicants could receive credit for actions that occurred prior to
the enactment of the Incentives Program that align with the desired outcomes
of the program, the Incentives Program would include a look-back period. The
look-back period would be defined as the time preceding the project sponsor’s
completed application during which the new revenue generation was
implemented. Subsequent applications in later years would add such additional
time to the time after enactment of the program. The look-back period would
be three years before the date of application to the program, and the
determination would be made based on the implementation date (or take effect
date) of the new revenue source. In evaluating applications, the project
sponsor’s new revenue application score would be multiplied by a relevant
multiplier to determine scoring as illustrated below:

4
New Revenue Credit
Years Passed Score Multiplier
>3 X percent
2-3 X percent
1-2 X percent
0-1 X percent
After February
100 percent
2018

 The lead Federal agency would have sole discretion to provide credit for
previous revenue generation. The agency could request additional information
from a project sponsor to clarify how the revenue source has met expectations
and revise forecasts to reflect actual performance. The amount of funds
dedicated to the look-back would not exceed 5 percent of the total amount for
the Incentives Program.

E. Incentive Grant Awards

 An incentive grant could not exceed 20 percent of new revenue.


 Any individual State could not receive more than 10 percent of the total amount
available under the Incentives Program.
 The lead Federal agency and the grant recipient would enter into an
infrastructure incentives agreement setting forth progress milestones toward
obtaining increased revenue that the recipient would achieve prior to receiving
the grant award, which could include advance grant disbursements.
 Any agreement with incomplete milestones after two years would be voided,
except upon determination by the lead Federal agency that good cause exists to
renew the agreement for an additional period not to exceed one year. Any funds
available from a voided agreement could be re-allocated through a new
application process.

II. RURAL INFRASTRUCTURE PROGRAM

The Rural Infrastructure Program, described, below would provide for significant
investment in rural infrastructure to address long-unmet needs. This investment is
needed to spur prosperous rural economies, facilitate freight movement, improve
access to reliable and affordable transportation options and enhance health and safety
for residents and businesses. Under this program, States would be incentivized to
partner with local and private investments for completion and operation of rural
infrastructure projects.

A. Establishment of Rural Infrastructure Program

This provision would establish a Rural Infrastructure Program to—


 improve the condition and capability of rural infrastructure through capital
improvements and outcomes-driven planning efforts that enhance private

5
sector productivity, modernize existing infrastructure systems, and prioritize
projects essential for efficiency and safety;
 expand access to markets, customers, and employment opportunities with
projects that sustain and grow business revenue and personal income for rural
Americans;
 enhance regional connectivity through public and private interregional and
interstate rural projects and initiatives that reduce costs for sustaining safe,
quality rural communities; and
 increase rural economic growth and competitiveness by closing local
infrastructure gaps in development-ready areas to attract manufacturing and
economic growth to rural America.
B. Applicability

 Eligible asset classes under the Rural Infrastructure Program would include:
o Transportation: roads, bridges, public transit, rail, airports, and maritime
and inland waterway ports.
o Broadband (and other high-speed data and communication conduits).
o Water and Waste: drinking water, wastewater, stormwater, land
revitalization and Brownfields.
o Power and Electric: governmental generation, transmission and
distribution facilities.
o Water Resources: flood risk management, water supply, and waterways.
 This program only would apply to the specified asset classes and to other
infrastructure assets directly attributable to, and essential to, the operation of
those assets.

C. Funding

 $50 billion would be made available to the Rural Infrastructure Program for
capital investments in rural infrastructure investments.
 80 percent of the funds under the Rural Infrastructure Program would be
provided to the governor of each State via formula distribution. The governors,
in consultation with a designated Federal agency and State directors of rural
development, would have discretion to choose individual investments to
respond to the unique rural needs of their States.
 20 percent of the funds under the Rural Infrastructure Program would be
reserved for rural performance grants within eligible asset classes and
according to specified criteria.
 Funds made available to States under this program would be distributed as
block grants to be used for infrastructure projects in rural areas with
populations of less than 50,000.
 A portion of the Rural Infrastructure Program funds would be set aside for
Tribal infrastructure and territorial infrastructure, with the remainder
available for States.
D. Distribution of Rural Infrastructure Program Formula Funds

6
 The statute would create a “rural formula,” calculated based on rural lane miles
and rural population adjusted to reflect policy objectives. Each State would
receive no less than a specified statutory minimum and no more than a
specified statutory maximum of the Rural Infrastructure Program formula
funds, automatically.

E. Applications and Evaluation Criteria for Rural Performance Grants

 In addition to receiving formula funds under the Rural Infrastructure Program,


States also could apply for rural performance grants and would be encouraged
to do so within two years after enactment. Rural performance grants would be
available for up to ten years after enactment or until funds were expended. In
order to qualify for rural performance grants, a State would be required to:
o Publish a comprehensive rural infrastructure investment plan (RIIP) within
180 days of receiving rural formula funds. The RIIP would demonstrate how
the State’s intended rural projects align with the evaluation criteria in the
infrastructure incentives program, including State, local and private sector
investment in eligible projects.
o Demonstrate the quality of any investments planned with rural
performance funds.
o Demonstrate performance in leveraging formula distributions with Federal
credit programs and rewarding rural interstate projects through the
infrastructure incentives program.
o Demonstrate the State’s performance in utilization of Rural Infrastructure
Program formula funds, consistent with the RIIP based on stated general
criteria.
 For specific sectors, a State also would demonstrate other criteria the
administering agency determines appropriate consistent with this program,
including increased broadband availability and investment.

F. Tribal Infrastructure

 The Rural Infrastructure Program also would ensure investment in Tribal


infrastructure by providing dedicated funding to the Secretary of
Transportation for distribution through the Tribal Transportation Program and
to the Secretary of Interior for distribution through grants or awards to Tribes
determined by a process created in consultation with Tribes.

G. Territorial Infrastructure

 The Rural Infrastructure Program also would provide dedicated funding to


address infrastructure needs of U.S. Territories.

III. TRANSFORMATIVE PROJECTS PROGRAM

7
The Transformative Projects Program, described below, would provide Federal
funding and technical assistance for bold, innovative, and transformative
infrastructure projects that could dramatically improve infrastructure. Funding
under this program would be awarded on a competitive basis to projects that are
likely to be commercially viable, but that possess unique technical and risk
characteristics that otherwise deter private sector investment. The
Transformative Projects Program would support projects that, with Federal
support, are capable of generating revenue, would provide net public benefits, and
would have a significant positive impact on the Nation, a region, State, or
metropolitan area.

A. Establishment of Transformative Projects Program

This provision would establish a program to advance transformative projects. The


purposes of the Transformative Projects Program would include—
 significantly improving performance, from the perspective of availability,
safety, reliability, frequency, and service speed;
 substantially reducing user costs for services;
 introducing new types of services; and
 improving services based on other related metrics.

B. Applicability

 The Transformative Projects Program would fundamentally transform the way


infrastructure is delivered or operated. They would be ambitious, exploratory,
and ground-breaking project ideas that have significantly more risk than
standard infrastructure projects, but offer a much larger reward profile.
 Infrastructure sectors covered by this program could include, but would not be
limited to, the transportation, clean water, drinking water, energy, commercial
space, and broadband sectors.

C. Funding

 $20 billion would be made available for the Transformative Projects Program.
 The Department of Commerce (DOC) would serve as the Chair for the purposes
of program administration and could request other relevant Federal agency
employees to serve on a temporary assignment to assist in the administration
of this program.
 A percentage of the Transformative Projects Program funds would be set aside
for temporary administrative expenses necessary to administer the program,
including technical assistance.

D. Funding Tracks

 Funding under this program would be available under three tracks, each of
which would be designed to support a distinct phase of the project life cycle:

8
demonstration, project planning, and capital construction. Applicants could
apply for funding under all three tracks or under individual tracks.
 To optimize the return on taxpayer investment, funding under this program
could be used for—
o up to 30 percent of eligible costs under the demonstration track;
o up to 50 percent of eligible costs under the project planning track; and
o up to 80 percent of eligible costs under the capital construction track.

E. Technical Assistance

 An applicant could seek technical assistance from the Federal Government in


addition to the funding tracks, or could seek technical assistance alone under
the Transformative Projects Program.

F. Applications and Evaluation Criteria

 The DOC would administer the Transformative Projects Program with an


interagency selection committee composed of representatives of relevant
Federal agencies. The Secretary of Commerce would serve as the chair of
the committee. Given the multidisciplinary nature of the Transformative
Projects Program, interagency evaluation panels comprised of individuals
from the applicable Federal agencies would review and evaluate all
applications.

G. Partnership Agreement and Project Milestones

 Applicants selected for award under the Transformative Projects Program


would enter into a partnership agreement with the Federal Government, which
would specify the terms and conditions of the award, major milestones, and
other key metrics to assess performance.

H. Value Sharing Structure for Capital Construction Track

 As a condition of receiving any financial assistance for a construction


project under the capital construction track, an applicant would be
required to include in its partnership agreement a value share agreement
with the Federal Government. The terms of the value share agreement
would vary by project based on the characteristics of the specific project
and its projected revenue profile. Each agreement would provide the
terms for the Federal Government to share in any project value.

I. Performance Monitoring and Oversight

 Given the innovation and substantial Federal support projects would receive
under this program, the recipients would be required to publish performance
information upon achieving milestones and upon project completion. The lead

9
Federal agencies also would conduct regular audits to ensure that funds were
used for eligible costs.

IV. INFRASTRUCTURE FINANCING PROGRAMS

The below infrastructure financing proposals would dedicate $20 billion of the overall
amount to advance major, complex infrastructure projects by increasing the capacity
of existing Federal credit programs to fund investments and by broadening the use of
Private Activity Bonds (PABs).
Of the appropriated funds, $14 billion would be made available for the expansion of
existing credit programs to address a broader range of infrastructure needs, giving
State and local governments increased opportunity to finance large-scale
infrastructure projects under terms that are more advantageous than in the financial
market. All funds remaining in credit programs ten years after enactment would be
diverted to the Federal capital financing fund, to allow for efficient acquisition of real
property.

The budgetary cost for the expansion of PABs would be $6 billion. These provisions
would provide tools and mechanisms for market participants to invest in public
infrastructure.

A. Expand Transportation Infrastructure Finance and Innovation Act (TIFIA)


Funding and Broaden Program Eligibility

 Additional budget authority would be made available to DOT for subsidy costs
under TIFIA. Specific funds set aside from the appropriated subsidy would be
appropriated to DOT, notwithstanding Section 2001 of the Fixing America’s
Surface Transportation Act of 2015, and would remain available until end of
Fiscal Year 2028.
 Support airport and non-Federal waterways and ports financing options. TIFIA
currently limits project eligibility to those that are eligible for Federal
assistance through existing surface transportation programs (highway projects
and transit capital projects). Port and airport infrastructure enhancement and
expansion projects across the United States do not have access to the credit
assistance that is available via TIFIA for other types of transportation
infrastructure projects, making it more difficult for project sponsors to pursue
alternative project delivery for airports and to implement critical airport
infrastructure improvements. Amending the project eligibility in the TIFIA
statute to enable TIFIA to offer loans and other credit assistance to non-Federal
waterways and ports and airport projects (such as renovated or new passenger
terminals, runways, and related facilities) would incentivize project delivery for
airports and ports and would accelerate overall improvements in airport and
seaport infrastructure.

B. Expand Railroad Rehabilitation and Improvement Financing (RRIF) and


Broaden Program Eligibility

10
 Additional budget authority would be made available to DOT for subsidy costs
under RRIF. Specific funds set aside from the appropriated subsidy would be
appropriated to DOT, notwithstanding Section 2001 of the Fixing America’s
Surface Transportation Act of 2015, and would remain available until end of
Fiscal Year 2028.
 Subsidize RRIF for short-line freight and passenger rail. The current RRIF law
does not provide specific subsidies or incentives for either short-line freight
rail or passenger rail projects. A subsidy is not currently provided to cover the
cost of the RRIF credit risk premium, so the project sponsor is always required
to pay that amount at the time of the loan disbursement. The cost of the credit
risk premium is often cited as one of the reasons that project sponsors,
including those in the short-line freight rail and passenger rail sectors, are
reluctant to pursue RRIF financing. Amending the law (45 U.S.C. 822) to
provide a subsidy to cover the RRIF credit risk premium for short-line freight
and passenger rail project sponsors would incentivize more project sponsors to
pursue RRIF credit assistance for projects. This, in turn, would leverage more
State and local funds for rail infrastructure development.

C. Expand Water Infrastructure Finance and Innovation Act (WIFIA) Funding


and Broaden Program Eligibility

 Additional budget authority would be made available to EPA for subsidy costs
under WIFIA, and the current lending limit of $3.2 billion would be removed.
Specific funds set aside from the appropriated subsidy would be appropriated to
the EPA, notwithstanding Section 5033 of the Water Infrastructure Finance and
Innovation Act of 2014, and would remain available until end of Fiscal Year
2028.
 This proposal includes the following additional reforms to WIFIA:
o Expand EPA’s WIFIA authorization to include non-Federal flood mitigation,
navigation and water supply. Currently, WIFIA is authorized for almost all
types of water projects. While EPA has drought mitigation and stormwater
mitigation authorities, it lacks authority for flood mitigation, hurricane and
storm damage reduction, navigation, environmental restoration, and
restoration of aquatic ecosystems (which has principally been within
USACE’s jurisdiction). This creates an unnecessary and arbitrary carve-out
of integrated water projects to which EPA is unable to provide loans because
those types of projects are not authorized by EPA, only by USACE.
Amending the law (33 U.S.C. 3905) to include flood mitigation, navigation
and water supply would allow EPA to service the full water cycle and provide
one streamlined and integrated lending process to project sponsors.
o Eliminate requirement under WIFIA for borrowers to be community water
systems. Currently, a public authority that sells water directly to another
water provider is not a community water system and is not eligible for
WIFIA funding unless specific statutory authority is provided. Without
explicit statutory eligibility, this type of public authority (e.g., a desalination

11
plant) is unable to receive WIFIA funding. Removing the restriction that
requires borrowers to be “community water systems” instead of just “water
systems” (33 U.S.C. 3905) would allow drinking water providers and other
public authorities to participate in WIFIA and the Drinking Water State
Revolving Fund (DWSRF) programs.
o Authorize Brownfield rehabilitation and cleanup of Superfund sites under
WIFIA. Currently, only specific water sector projects are authorized under
WIFIA. Brownfield and Superfund programs do not have access to a Federal
lending program that requires large upfront funding and repayment based
on later development. Broadening eligibility under WIFIA (33 U.S.C. 3905)
to include remediation of water quality contamination by non-liable parties
at Brownfield and Superfund sites would enable greater use of the program
to address water quality issues. A separate account would be appropriate for
individual eligibilities and ranking metrics because new revenues would be
more speculative and would lower the leveragability ratio for all WIFIA
loans.
o Reduce rating agency opinions from two to one for all borrowers. Current law
requires borrowers to provide two opinion letters from rating agencies for
WIFIA loans. Opinion letters can be expensive and time intensive for
borrowers to obtain. Reducing from the number of required rating agency
final opinions for borrowers (33 U.S.C. 3907) to allow for one opinion letter
instead of two would reduce WIFIA borrowing costs for borrowers. At the
same time, retaining agency authority to request two letters from a
borrower under WIFIA would ensure continued protection of Federal
interests and would minimize default risk when a project warrants a second
letter.
o Provide EPA authority to waive the springing lien in certain lending situations.
Currently, loans under WIFIA must have a springing lien in place. This is a
problem when a project sponsor has outstanding senior debt obligations.
Without a waiver to the springing lien requirement, the sponsor has to use
more expensive debt, and WIFIA has less security in the special purpose
vehicle. Amending the law (33 U.S.C. 3908(b)) to allow for a waiver of the
WIFIA springing lien in certain instances similar to the TIFIA statute (23
U.S.C. 603(b)) (i.e., where a project has an A category rating, where the
pledge is not dependent on project revenue, or where the borrower is a
public sector borrower) would allow for the most efficient capital structure
for agencies with existing senior debt.
o Increase the base level of administrative funding authorized to ensure EPA has
sufficient funding to operate the WIFIA program. The current authorized
administrative funds level for EPA was determined when WIFIA was a pilot
program and may not be sufficient to cover both administrative costs and
the fronting of underwriting costs, especially with our proposed expansion
of WIFIA. Authorizing an administrative set-aside (33 U.S.C. 3912(b)) to an
amount in line with similar programs would more accurately reflect the
costs required to administer the WIFIA program and would allow for hiring
appropriate staff for the oversight efforts associated with a larger portfolio.

12
o Remove the restriction on the ability to reimburse costs incurred prior to loan
closing under WIFIA. A recent amendment to WIFIA restricts the WIFIA
program’s ability to reimburse costs incurred prior to loan closing. This
amendment, part of the Water Infrastructure Improvements for the Nation
Act (WIIN Act), attempts to ensure that costs incurred prior to loan closing
may be considered eligible project costs. However, the WIIN amendment
only allows non-WIFIA funds to reimburse the costs. Revising the law (33
U.S.C. 3908(b)) to provide that costs incurred prior to loan closing are
eligible costs that can be covered by the WIFIA loan would prevent the
borrower from having to raise significant sums of money prior to loan
closing.
o Expand the WIFIA program to authorize eligibility for credit assistance for water
system acquisitions and restructurings. Currently, projects only are allowed to
access WIFIA for acquisitions of water systems prior to substantial
completion, similar to TIFIA. This prevents WIFIA funds from being used
for acquisition of water systems after they are completed, or substantially
completed. Expanding WIFIA authorization (33 U.S.C. 3905) to allow for
acquisitions and restructurings would enable WIFIA as a mechanism for
consolidation in the water industry.
o Expand WIFIA authorization to include Federal deauthorized water resource
projects. Currently, WIFIA is authorized for non-Federal water resource
projects unless they are deemed Federal projects. Once deemed Federal, a
project is no longer eligible for WIFIA borrowing, even if no Federal funding
is used. This hinders the ability to incentivize non-Federal involvement for
USACE projects. Authorizing USACE to defederalize water resource projects
upon transfer of title and ownership from the Federal Government to a
willing and capable non-Federal entity would enable WIFIA to be used for
these projects.

D. Expand Department of Agriculture Rural Utilities Service (RUS) Lending


Programs Funding

 Additional budget authority would be made available to the USDA for loan
subsidy costs under RUS lending programs. Specific funds set aside from the
appropriated subsidy would be made available to the USDA, notwithstanding
applicable sections of the Agriculture Act of 2014, and would remain available
until end of Fiscal Year 2028.

E. Create Flexibility and Broaden Eligibility to Facilitate use of Private Activity


Bonds (PABs)

 These provisions would create flexibility and broaden eligibility to facilitate use
of PABs to leverage financing for public-purpose infrastructure projects. These
provisions also would allow for greater Federal leverage and therefore more
efficient infrastructure improvements.

13
 Require public attributes for public infrastructure projects. In extending tax
exemptions to private enterprises, tax benefits could go to purely private
enterprises, which would not be beneficial to the public or a sound use of public
tax benefits. Requiring public infrastructure projects to have the following
public attributes would ensure the public nature of eligible infrastructure—
o either State or local governmental ownership or private ownership under
arrangements in which rates charged for services or use of projects are
subject to State or local governmental regulatory or contractual control or
approval; and
o availability of projects for general public use (e.g., public roads) or provision
of services to the general public (e.g., water service).
For purposes of the governmental ownership alternative under the public
attributes requirement, a new safe harbor would treat a project as
governmentally owned when a State or local governmental unit leases the
project to a private business provided that—
o the term of the private lease is no longer than 95 percent (rather than 80
percent under the existing safe harbor) of the reasonably expected
economic life of the project;
o the private lessee irrevocably agrees not to take depreciation or investment
tax credit with respect to the project; and
o the private lessee has no option to purchase the project other than at fair
market value.
 Broaden eligibility of PABs. Current law includes a limited list of exempt
facilities eligible to be financed with tax-exempt bonds. Additionally, different
categories of exempt facilities are subject to varying requirements, which
restricts the usefulness of PABs. This limits the potential financing tools that
can be used to facilitate performance-based infrastructure, both for a wide
variety of transportation projects and other public-purpose infrastructure
projects. The revised parameters would allow longer-term private leases and
concession arrangements for projects financed with PABs. Amending the law
(26 U.S.C. 142) to allow broader categories of public-purpose infrastructure,
including reconstruction projects, to take advantage of PABs would encourage
more private investment in projects that benefit the public. Allowing privately
financed infrastructure projects to benefit from similar tax-exempt financing
as publicly financed infrastructure projects would increase infrastructure
investment. This proposal would expand and modify eligible exempt facilities
for PABs to include the following public infrastructure projects.
o Existing categories:
 airports (existing category);
 docks, wharves, maritime and inland waterway ports, and
waterway infrastructure, including dredging and navigation
improvements (expanded existing category);
 mass commuting facilities (existing category);
 facilities for the furnishing of water (existing category);
 sewage facilities (existing category);
 solid waste disposal facilities (existing category);

14
o Modified categories:
 qualified surface transportation facilities, including roads,
bridges, tunnels, passenger railroads, surface freight transfer
facilities, and other facilities that are eligible for Federal credit
assistance under title 23 or 49 (i.e., qualified projects under TIFIA)
(existing category with modified description);
 hydroelectric power generating facilities (expanded existing
category beyond environmental enhancements to include new
construction);
 flood control and stormwater facilities (new category);
 rural broadband service facilities (new category); and
 environmental remediation costs on Brownfield and Superfund
sites (new category).
 Eliminate the Alternative Minimum Tax preference on PABs. One reason why
PABs have been underutilized is due to the punitive market interest rate effect
of the Alternative Minimum Tax (AMT) tax preference on PABs, which adds an
estimated 30-40 basis points (0.30-0.40 percent) yield premium to the
borrowing rate for PABs compared to traditional governmental municipal
bonds due to the more limited demand. This creates inconsistent premiums for
service providers and disincentives for borrowers to use this financing
mechanisms. Eliminating the AMT preference on PABs would lower borrowing
costs and increase the utilization of PABs.
 Remove State volume caps and transportation volume caps on PABs for public
purpose infrastructure projects and expand eligibility to ports and airports. Clean
water and drinking water projects currently are subject to State volume caps for
PABs, based on population. In recent years, as little as 1-1.5 percent of all
exempt bonds were issued to water and wastewater projects. Exceptions from
the volume cap currently are provided for other governmentally owned
facilities such as airports, ports, housing, high-speed intercity rail, and solid
waste disposal sites. Additionally, many performance-based infrastructure
projects for transportation facilities described in 26 U.S.C. 142(m) have taken
advantage of PABs, which allow private sector developers to benefit from
similar tax-exempt subsidies provided to public sector borrowers. The law
establishes a nationwide volume cap of $15 billion for these projects, to be
allocated by the Secretary of Transportation.
o These caps create uncertainty as to the availability of PABs in the future, as
projects require long lead times for development, and no additional PABs
may be issued for this type of facility once the cap has been exhausted.
o Amending 26 U.S.C. 146 to remove the population-based volume cap
applicable to PABs for public purpose infrastructure projects of the types
covered by this proposal that have the requisite public attributes would level
the playing field between public and private service providers.
o Amending 26 U.S.C. 142(m) to eliminate the nationwide cap would provide
certainty that PABs would be available to a project sponsor as it developed
and evaluated a project’s financial strategy. This provision would apply
only if a State volume cap did not already apply.

15
 Provide change-of-use provisions to preserve the tax-exempt status of
governmental bonds. Currently, when a public project is purchased by a private
service provider, the tax-exempt status is eliminated when the private use
limits on government bonds are exceeded. This creates a structural barrier to
the private sector acquiring projects because that cost premium must be funded
at closing. Adding change-of-use curative provisions (26 U.S.C. 150) to protect
the tax-exempt status of governmental bonds in transactions involving private
business use of projects financed with governmental bonds that otherwise
would violate private business use limits on those bonds (e.g., private leases)
would eliminate this private sector barrier. One curative action would allow
alternative business use of the public project in a manner that would qualify as
an infrastructure project eligible for a new issuance of PABs under the proposal.
Another curative action would allow recycling of an amount equal to the total
present value of a private lease of any project financed with governmental
bonds into expenditures for governmental use within two years of the lease.
 Provide change-of-use cures for private leasing of projects to ensure preservation
of tax exemption for infrastructure projects. Currently, Treasury regulations allow
certain change-of-use remedial actions to preserve the tax exemption for the
tax-exempt governmental bonds upon a violation of private business use
restrictions. Existing remedial actions include: defeasance of the outstanding
bonds, “recycling” amounts received to qualifying government uses within two
years, or alternative use of a project in a way that would qualify for tax-exempt
bonds (including PABs) if retested at the time of use. These change-of-use
cures do not include private leasing as a remedial action that would preserve
tax-exempt status of the bonds. Therefore, the private sector market
participants are not able to access the tax-exempt debt market for public
infrastructure. Providing for tailored change-of-use remedial actions that
preserve the tax exemption status upon private leasing of projects subject to
outstanding tax-exempt government bonds or allowing “recycling” the total
present value of the private lease payments into public and governmental uses
within two years would ensure the assets retain the tax-exempt status of the
associated debt obligations.

V. PUBLIC LANDS INFRASTRUCTURE

The below public lands provisions would enable the additional revenues generated
from energy development on public lands to pay for capital and maintenance needs of
public lands infrastructure. The Department of the Interior (DOI) manages an
extensive infrastructure asset portfolio. The infrastructure managed by the DOI
includes approximately 100,000 miles of roads as well as dams, bridges, and irrigation
and power infrastructure. Taking care of this significant asset portfolio is a persistent
challenge. The National Park Service (NPS) has a deferred maintenance backlog of
$11.3 billion, half of which is for roads, bridges and tunnels, and the U.S. Fish and
Wildlife Service also has a deferred maintenance backlog of $1.2 billion. To address
this infrastructure need, this provision would establish a new infrastructure fund in
the U.S. Treasury entitled the Interior Maintenance Fund (Fund) comprised of

16
additional revenues from the amounts due and payable to the United States from
mineral and energy development on Federal lands and waters.

A. Establish Interior Maintenance Fund

 Currently, receipts generated from mineral and energy development on public


lands are not available for capital and maintenance of public infrastructure.
 This limitation perpetuates the deferred maintenance backlog for public lands
infrastructure.
 Allowing half of additional receipts generated by expanded Federal energy
development to be deposited into the Fund would help the DOI address this
backlog. Such receipts would be deposited into the Fund until the cumulative
amount deposited had reached $18 billion.
 The receipts deposited in the Fund would be made available to the Secretary of
the Interior, without fiscal year limitation, to address the deferred maintenance
and capital needs for infrastructure in national parks and wildlife refuges.
 The DOI would use its capital asset management systems to prioritize projects,
monitor implementation, and measure results.

VI. DISPOSITION OF FEDERAL REAL PROPERTY

The below provisions would establish authority to allow for the disposal of Federal
assets to improve the allocation of economic resources in infrastructure investment.

A. Codify Accelerated Depreciation for the Disposition of Non-Federal Assets


with a Federal Interest Due to Grant Receipt

 Currently, it is unclear which disposition actions utilities and municipalities


may have undertaken with assets funded by Federal construction grants and
earmarks. Prior to Executive Order 12803—Infrastructure Privatization (1992)
—the federally funded share of any disposed asset was to be returned to
Treasury.
 This lack of clarity results in project sponsors not understanding their
responsibilities and benefits when disposing of federally funded assets and
some sponsors choosing not to dispose of assets due to incorrect assumptions.
 Codifying Executive Order 12803 would allow accelerated depreciation for the
disposition of non-Federal assets and application of those rules to any
dispositions undertaken since issuance of the Executive Order. Directing the
agencies to provide guidance on implementation also would provide clarity for
utilities and municipalities when divesting or privatizing assets.

B. Streamline and Improve the Federal Real Property Disposal Process

 The current statutory disposal process for real property is governed primarily
by title 40 of the United States Code, with many requirements that are
burdensome and delay sale or disposal of federally owned assets.

17
 The Federal real property civilian inventory is comprised of facilities with an
average age of 47 years, many of which are inefficient and outdated. Today,
agencies require more flexible work environments; however, the Government
largely is unable to tap into the value of the portfolio due to the current
statutory limitations.
 Amending the statute to allow agencies to move property to market more
quickly and retain the gross proceeds of sale would allow the Government to be
more nimble and lower costs.
o Allow the Government to take assets no longer needed by any Federal agency
directly to market. Currently, title 40 of the United States Code requires
agencies to screen a potential disposal for at least 12 public benefit
conveyance requirements. State and local governments and certain non-
profit institutions may acquire surplus real property at discounts of up to
100 percent for various types of public use. This process can take years to
complete. Allowing the Government to take assets no longer needed by any
Federal agency directly to market would allow any interested party to
purchase assets at fair market value without any preferences or right of first
refusal.
o Retain proceeds for reinvestment in agency real property requirements. Under
current law, most agencies lack retention of proceeds authority, and nearly
all agencies with retention authority require an appropriation to access the
funds. This creates a disincentive to agency disposition action and prevents
reinvestment in mission-critical Federal facilities. Amending the statute to
allow retention of proceeds and expenditure without future authorization or
appropriation would allow agencies to take immediate action reinvesting in
critical real property assets, reconfiguring space to improve utilization and
lower costs, and disposing of additional unneeded assets. This provision
also would allow proceeds to be retained without fiscal year limitation.
o Expand the allowable uses of the General Services Administration (GSA)
Disposal Fund. Current authority limits GSA assistance to other Federal
agencies for those activities that occur after a report of excess (which
highlights unneeded real property). GSA does not have authority to help
agencies on activities that prepare for the report of excess, which inhibits
the agencies’ ability to dispose of assets. Additionally, agencies do not
always complete these activities because agencies must fund them from
their limited resources. Expanding authority to allow GSA to support
activities that occur prior to the report of excess, including identifying,
preparing, and divesting properties prior to the report of excess, would
reduce the Federal footprint and allow more efficient asset management.
Under this provision, the same account properties would remain, allowing
GSA to recover costs from the gross proceeds prior to agency retention.
o Eliminate the requirement to transfer funds above the identified threshold to the
Land and Water Conservation Fund. Current non-GSA property disposal
under title 40 requires a transfer to the Land and Water Conservation Fund.
Eliminating the requirement to transfer funds above the identified

18
threshold to the Land and Water Conservation Fund would maximize the
funds available to support disposition actions.

C. Authorize Federal Divestiture of Assets that Would Be Better Managed by


State, Local, or Private Entities

 The Federal Government owns and operates certain infrastructure that would
be more appropriately owned by State, local, or private entities.
 For example, the vast majority of the Nation’s electricity needs are met through
for-profit investor-owned utilities. Federal ownership of these assets can
result in sub-optimal investment decisions and create risk for taxpayers.
 Providing Federal agencies authority to divest of Federal assets where the
agencies can demonstrate an increase in value from the sale would optimize the
taxpayer value for Federal assets. To utilize this authority, an agency would
delineate how proceeds would be spent and identify appropriate conditions
under which sales would be made. An agency also would conduct a study or
analysis to show the increase in value from divestiture. Examples of assets for
potential divestiture include—
o Southwestern Power Administration’s transmission assets;
o Western Area Power Administration’s transmission assets;
o Ronald Reagan Washington National and Dulles International Airports;
o George Washington and Baltimore Washington Parkways;
o Tennessee Valley Authority transmission assets;
o Bonneville Power Administration’s transmission assets; and
o Washington Aqueduct.

VII. FEDERAL CAPITAL FINANCING FUND

Before an agency can purchase real property, it must receive an appropriation for the
full purchase price. The full appropriation scores in that year against the
discretionary caps and against the maximum funding (the 302(b) allocation) that the
Appropriations Subcommittee can provide. This is problematic for large-dollar,
irregular acquisitions because they must compete with agency operating and
programmatic expenses for the limited resources available. The below provisions
would create a funding mechanism to address this issue.

A. Create Federal Capital Financing Fund

 Too often, tight spending limits mean that purchases are not funded, and
agencies must resort to signing long-term leases. These are always more
expensive to taxpayers over the long run because Treasury can always borrow
at the lowest rate. Because rent is obligated one year at a time, the lease
payments can fit within an agency’s budget without disrupting other needs. In
contrast, private firms and State and local governments budget for purchases of
real property in separate capital budgets so that real property purchases do not
compete with annual operating needs. Their system allows proposed purchases

19
to be compared to each other and ranked such that the ones with the highest
return on investment are funded within the total capital budget.
 This provision would create a funding mechanism that is similar to a capital
budget but operates within the traditional rules used for the Federal budget by
establishing a mandatory revolving fund to finance purchases of federally
owned civilian real property. Of the total appropriation, $10 billion would be
made available to capitalize the revolving fund. Upon approval in an
Appropriations Act, the revolving fund would transfer money to agencies to
finance large-dollar real property purchases. Purchasing agencies would then
be required to repay the fund in 15 equal annual amounts using discretionary
appropriations.
 As a result, purchases of real property assets would no longer compete with
annual operating and programmatic expenses for the limited funding available
under tight discretionary caps. Instead, agencies would pay for real property
over time as the property were utilized. The repayments would be made from
future appropriations, which would provide an incentive to select projects with
the highest return on investment, including future cost avoidance. The
repayments also would replenish the revolving fund so that real property could
continually be replaced as needed.

PART 2—ADDITIONAL PROVISIONS FOR INFRASTRUCTURE IMPROVEMENTS

I. TRANSPORTATION

These provisions would incentivize and remove barriers to the development and
improvement of transportation infrastructure in our Nation. These provisions would
encourage and incentivize alternative project delivery, including State, tribal, local
and private investment, in transportation; streamline Federal procedures for
delivering transportation projects; and decrease barriers and reduce unnecessary
Federal oversight to facilitate timely delivery of projects. This renewed investment in
transportation would strengthen our economy, enhance our competitiveness in world
trade, create jobs and increase wages for our workers, and reduce the costs of goods
and services for our families.

A. Financing

1. Provide States Tolling Flexibility

 Provide States flexibility to toll on Interstates and reinvest toll revenues in


infrastructure. Currently, Federal law allows tolling Interstates in limited
circumstances. Tolling restrictions foreclose what might otherwise serve as a
major source of revenue for infrastructure investment. Providing States
flexibility to toll existing Interstates would generate additional revenues for
States to invest in surface transportation infrastructure. Current requirements
that States must reinvest toll revenues in infrastructure would continue to
apply.

20
 Reconcile the grandfathered restrictions on use of highway toll revenues with
current law. Toll facilities that received Federal approval under the Surface
Transportation and Uniform Relocation Assistance Act of 1987 (STURRA) may
use toll revenues only for the construction, reconstruction, operation, and debt
service of the toll facility itself. Current law, however, allows other toll
facilities to use toll revenues (in addition to the costs noted above) on other
title 23 projects. The tighter restrictions, specific to the STURRA toll facilities,
prevent some States from devoting existing toll revenues to other critical
highway projects. Adjusting the STURRA “use of revenues” provisions to align
with current toll authorities would free these resources and allow other critical
highway projects to go forward.

2. Extend Streamlined Passenger Facility Charge Process from Non-hub Airports to


Small Hub Airports

 Current law (49 U.S.C. 40117) outlines the application process to impose
passenger facility charges (PFCs), as well as the approval process and pilot
program for alternative procedures. Small, medium, and large hub airports
must provide extensive documentation in PFC applications to demonstrate the
eligibility, justification, objective, project costs, significant contribution (large
and medium hubs) and other requirements. The streamlined non-hub process
requires reduced information, primarily relating to project descriptions and
costs.
 Current law creates an unreasonable burden on small hub airports filing PFC
applications.
 Extending the streamlined PFC process to small hub airports would allow these
airports to more readily fund needed development as well as reduce delays and
unnecessary requirements in the PFC process.

3. Provide States Flexibility to Commercialize Interstate Rest Areas

 Federal law prohibits most commercial activity within the Interstate right-of-
way, including at Interstate rest areas.
 This limits infrastructure investment opportunities and the ability to generate
revenues to operate and maintain Interstates.
 Amending the law (23 U.S.C. 111) to provide States flexibility to commercialize
Interstate rest areas, and requiring the revenues to be reinvested in the corridor
in which they are generated, would support new infrastructure investment.
States would not be permitted to charge fees for essential services such as water
or access to restrooms.

4. Provide New Flexibility for Transportation Projects with De Minimis Federal Share

 Under current law, even when a State or private sector entity provides the
majority of the funding for a project, it still must seek review and approval
under the laws of any Federal agency with jurisdiction.

21
 The additional procedures, costs and time delays associated with Federal
requirements discourage infrastructure investments by State and local entities
and private investors. Federal requirements also contribute to unnecessary
delays in delivering needed projects even when the Federal interest is small.
 Amending titles 23 and 49 to provide targeted flexibility pertaining to the
application of Federal requirements where the project funding is primarily
non-Federal and the Federal share is minimal would increase investments in
infrastructure and reduce project delays and costs.

5. Expand Qualified Credit Assistance and Other Capabilities for State Infrastructure
Banks

 State infrastructure banks (SIBs) currently are underutilized.


 This underutilization can inhibit State and local governments from best
directing Federal funds to infrastructure projects.
 Providing incentives to use SIBs, such as reducing federalization requirements
on funds lent to SIBs that are deployed locally, could encourage the use of SIBs.
Expanding the legal capabilities of SIBs, in addition to direct appropriations,
would allow SIBs to take responsibility for infrastructure funding in an
effective manner that may not be possible for the Federal Government,
particularly for rural projects or projects of smaller total cost.

B. Highways

1. Authorize Federal Land Management Agencies to Use Contracting Methods


Available to States

 Current law authorizes State departments of transportation (State DOTs) and


local governments to use a range of commonly used project delivery methods
(e.g., electronic bidding, bridge bundling, project bundling, construction
manager-general contractor), but does not authorize Federal Land
Management Agencies (FLMAs) to use these same methods—even when the
FLMAs are delivering projects with title 23 funds.
 This constrains FLMAs’ procurement options, which in some cases increases
the cost or timeline for delivering Federal lands highway projects.
 Expanding to FLMAs all title 23 contracting methods (for projects funded with
title 23 funds) would enable more efficient delivery of these projects.

2. Raise the Cost Threshold for Major Project Requirements to $1 Billion

 Current law (23 U.S.C. 106(h)) defines a major project as any project that
receives Federal financial assistance and has an estimated total project cost of
$500 million or more. Financial plans and project management plans must be
submitted to the Federal Highway Administration (FHWA) for all major
projects.

22
 For projects that are routinely managed by FHWA and State DOTs, these
requirements do very little to ensure the success of the project. Instead, the
requirements create an administrative burden that wastes resources and delays
project delivery.
 Amending the law to raise the threshold for major projects from $500 million
to $1 billion would remove unnecessary oversight requirements from smaller,
less complex projects that are routinely managed by FHWA and State DOTs.

3. Authorize Utility Relocation to Take Place Prior to NEPA Completion

 Current law requires any utility relocation to occur after completion of the
NEPA review process. Utility relocation is similarly restricted for transit
projects.
 Most projects with pre-construction activities include utility relocation, which
typically is a long lead item that cannot start until NEPA is completed. This
contributes to construction delays and cost escalation.
 Amending the law to allow utility relocation to take place prior to NEPA
completion would streamline the building process, reduce overall construction
time, and lower costs. Under this proposal, appropriate limitations would be
included to ensure the integrity of the NEPA process, such as making the
reimbursement of costs incurred dependent on the selection of an alternative
that requires the utilities to be relocated. Relocation costs only would be
reimbursed if a project were completed.

4. Authorize Repayment of Federal Investment to Eliminate Perpetual Application of


Federal Requirements

 Projects that use of Federal-aid highway funds for the construction of a


highway or bridge are constrained by Federal requirements. Many of these
requirements continue to apply to the facility after the project is
complete. These requirements include restrictions on tolling; requirements
pertaining to the location of a commercial plaza within the right-of-way of an
Interstate highway; restrictions on Interstate access; and compliance with size
and weight standards, highway beautification standards, and high occupancy
vehicle lane operation standards.
 These perpetual Federal requirements can inhibit a State’s ability to obtain
value from the facility and have flexibility with respect to its future operations
and maintenance. In the past, whenever a State wished to be released from the
application of these requirements, Congress enacted a specific statutory
provision that permitted the State to refund the Federal investment in that
facility. Upon repayment of Federal funds, the State was relieved of compliance
with the Federal requirements that attached to the facility.
 Amending the law to provide general authority for States to repay the Federal
investment in a facility would provide States with the ability to obtain value
from their assets and flexibility in how their highways and bridges are operated
and maintained. The repayment of Federal funds invested in a facility would be

23
the actual amount of Federal investment, unadjusted for inflation. Any funds
repaid in this manner would be credited to the Highway Trust Fund, and the
State would receive an equal amount of funding (available for obligation) under
the Surface Transportation Block Grant Program.

5. Provide Small Highway Projects with Relief for the Same Federal Requirements as
Major Projects

 Currently, some smaller scale projects (e.g., those typically eligible for
transportation alternatives) funded under the Surface Transportation Block
Grant Program must be treated as major highway projects, even if they are not
located within the right-of-way of a Federal-aid highway (23 U.S.C. 133).
 This means that smaller, simpler projects that could be implemented and open
to the public quickly often are delayed by lengthy procurement procedures and
Federal requirements that are more appropriate for larger, more complex
projects.
 Amending this requirement for smaller projects that predominantly are outside
the Federal-aid highway right-of-way would eliminate Federal procurement
requirements for these infrastructure projects. This would allow States to use
their own procedures to implement these projects.

C. Transit

1. Require Value Capture Financing as Condition of Receipt of Transit Funds for Capital
Investment Grants

 Federal programs for transit capital projects do not require value capture
financing. Current law includes a broad definition of “value capture” to mean
“recovering the increased property value to property located near public
transportation resulting from investments in public transportation.” (49 U.S.C.
5302(24)). Value capture can include joint development, land value taxes, tax
increment financing, special assessment districts, transportation utility fees,
development impact fees, negotiated extractions, transit oriented
development, and air rights.
 Failure of transit authorities to use value capture financing reduces funds
available for transit capital projects.
 Amending the law to include value capture financing as a prerequisite for
Section 5309 Capital Investment (Discretionary) Grants, excluding Small Starts
projects, would increase resources available for transit capital projects and
decrease dependence on Federal grant programs for continued development.

2. Eliminate Constraints on Use of Public-Private and Public-Public Partnerships in


Transit

24
 Current law (49 U.S.C. Chapter 53 and its implementing regulations) impedes
the greater use of public-private and public-public partnerships in transit
capital projects.
 These constraints reduce the funds available for transit capital projects.
 Eliminating these constraints would encourage greater investment in transit
capital projects.

3. Codify Expedited Project Delivery for Capital Investment Grants Pilot Program

 Currently, the Federal Transit Administration’s (FTA) framework for public-


private partnerships is a non-codified pilot program limiting the number of
projects eligible to participate and capping the Federal share at 25 percent
(Section 3005(b) of the FAST Act). The program also requires participants to
utilize existing union staff.
 The current pilot program is structured to offer participants a more
streamlined approach to the full-funding grant agreement approval process
and broader authority to proceed with construction. These attributes are
appealing to potential concessionaires and State and local jurisdictions.
However, the constraints placed on the program undermine the goals of
expediting project delivery.
 Codifying the pilot program, ensuring it is allowable for all Capital Investment
Grant projects and not just on a pilot basis, and increasing the Federal share to
50 percent would attract increased private investment and further expedite
project delivery.

D. Rail

1. Apply FAST Act Streamlining Provisions to Rail Projects and Shorten the Statute of
Limitations

 The FAST Act directed DOT to review all previously enacted highway permit
reforms and project streamlining procedures under title 23 and to apply them
to railroad projects under jurisdiction of the DOT.
 This created a discrepancy between a two-year statute of limitations for rail
projects and a 150-day statute of limitations for transit and highway projects.
In addition, this created a discrepancy between railroad projects administered
by DOT and many large railroad
projects administered by agencies other than the DOT (e.g., USACE and the
United States Coast Guard) which are not subject to the FAST Act streamlining
provisions under title 23.
 Amending the law to clarify that all rail projects, regardless of lead Federal
agency, can take advantage of FAST Act streamlining provisions would help
expedite rail project delivery. Amending the statute of limitations from two
years to 150 days for rail projects would make the time frame for legal
challenges on rail projects consistent with those for transit and highway
projects.

25
E. Airports

1. Create More Efficient Federal Aviation Administration Oversight of Non-aviation


Development Activities at Airports

 The Federal Aviation Administration (FAA) has conducted long-standing


reviews of projects other than critical airfield infrastructure (including
terminals, access and service roads, hangars, and other types of facilities)
(based on statutory requirements set forth in 49 U.S.C. Chapter 471, particularly
Sections 47102-47113 and Section 50101).
 This burdens FAA to review projects other than critical airfield infrastructure,
and as a result, slows project delivery.
 Amending the law (49 U.S.C. 47107) to limit FAA approval and oversight of non-
aviation development activities at airports would create more efficient FAA
oversight of critical airfield infrastructure.

2. Reduce Barriers to Alternative Project Delivery for Airports

 Current law (49 U.S.C. 47134) provides that, under an existing pilot program, 65
percent of carriers at an airport must approve privatization to privatize an
airport. The current pilot program is limited to only 10 airports, including only
one large hub airport.
 The pilot program allows individual air carriers to overturn an airport’s desire
to privatize, blocking private investments in airports.
 Removing the limitation on the number and size of airports that can participate
in the pilot program and decreasing the percentage of airlines needed to
approve privatization from 65 percent to a majority vote would reduce barriers
to alternative project delivery for airports and provide more flexibility for
carriers to approve privatization.

3. Clarify Authority for Incentive Payments under the Airport Improvement Program

 Currently, the Airport Improvement Program (AIP) does not allow incentive
payments for accelerated construction.
 This adds time to AIP projects, since they cannot pay for accelerated
completion.
 Clarifying the authority under the AIP (49 U.S.C. 47110) to permit additional
financial incentives, along with profit margin, for contractors would increase
work efficiency and reduce project completion times.

4. Move Oversight of AIP Funds to Post-expenditure Audits

 Current law (49 U.S.C. 47104-47106) requires FAA to review and approve grant
applications under the AIP.

26
 This oversight sometimes causes delays in sponsors receiving funds assigned
to their airports.
 Revising the statutory requirements for AIP to shift FAA oversight from grant
applications to post-expenditure audits would expedite conveyance of funds to
sponsors.

II. WATER INFRASTRUCTURE

The below water infrastructure provisions would incentivize the development of


effective and efficient water infrastructure, outcome-based procurement, and full
life-cycle asset management to improve water infrastructure. These changes would
provide greater flexibilities for USACE and its non-Federal partners to use available
Federal and non-Federal funds, generate new revenues and retain certain revenues in
support of project requirements, make greater use of contributed funds, and allow for
innovative use of contracting tools.

A. Financing

1. Authorize Clean Water Revolving Fund for Privately Owned Public-purpose


Treatment Works

 Current law allows the DWSRF to lend to private owners. However, the Clean
Water State Revolving Fund (CWSRF) is generally restricted to publicly owned
wastewater projects.
 Privately owned public-purpose treatment works are not eligible for CWSRF
funding at the Federal level.
 Authorizing the CWSRF (33 U.S.C. 1383) to provide financial assistance to
publicly owned and privately owned public-purpose treatment works would
make more funding available for treatment works.

2. Provide New Flexibility for Water Projects with De Minimis Federal Share

 Under current law, even when a State or private sector entity provides the
majority of the funding for a project, a project must still obtain review and
approval under the laws of any Federal agency with jurisdiction.
 The additional procedures, costs, and time delays associated with Federal
requirements discourage infrastructure investments by State and local entities
and private investors. These legal restrictions also contribute to delays in
delivering needed projects even when the Federal interest is small.
 Amending the law to provide targeted flexibility pertaining to the application of
Federal requirements where the project funding is primarily non-Federal and
the Federal share is minimal would increase investments in water
infrastructure and reduce project delays and costs.

B. Water Programs

27
1. Provide EPA Infrastructure Programs with “SEP-15” Authorizing Language

 Currently, the EPA Administrator has limited authority to test and experiment
within its programs.
 This limits the EPA’s ability to explore new approaches that might increase
project management flexibility, increase innovation, improve efficiency, assure
timely project implementation, and develop new revenue streams.
 Providing the EPA Administrator authority (similar to 23 U.S.C. 502) to
encourage tests and experimentation in the water projects development
process to permit the Administrator to explore alternative and innovative
approaches to the overall project development process and to develop more
effective approaches to project planning, project development, finance, design,
construction, maintenance, and operations.

2. Apply Identical Regulatory Requirements to Privately Owned Public-purpose


Treatment Works and Publicly Owned Treatment Works

 Currently, different requirements may apply to privately versus publicly owned


treatment works.
 This creates an unnecessary market distortion that puts private treatment
works under more stringent and costly regulatory requirements than public
sector equivalents, despite both serving public communities.
 Modifying the Clean Water Act to ensure identical requirements apply to
privately owned public-purpose treatment works and privately owned
treatment works would provide a level playing field for all service providers.

C. Inland Waterways

1. Expand Authority Related to Non-Federal Construction and Operation of Inland


Waterways Projects

 Currently, Congress individually authorizes inland waterways projects to be


constructed, maintained and operated by USACE. Only USACE is authorized to
use funds appropriated from the Inland Waterways Trust Fund (IWTF) or from
the General Fund (GF) of the Treasury for construction, repair, rehabilitation,
maintenance, and operation of inland waterways projects. Fuel taxes paid by
commercial users of the inland waterway system contribute to the IWTF, which
pays for 50 percent of construction and major rehabilitation on the system,
with the rest coming from the General Fund; once completed, project
maintenance and operations are entirely paid for from the General Fund.
 This means that only USACE can perform construction and operations, even if
there is a less costly alternative. In addition, this constrains projects to USACE
operational capacity limits, which has resulted in a backlog of projects and
deferred maintenance, lower operational effectiveness, and increased down
time of waterway assets.

28
 Authorizing the Secretary of the Army to execute agreements with non-Federal
public or private entities to use IWTF and GF funds for construction, repair,
rehabilitation, maintenance and operation activities, and the ability to enter
into third party contracts, concessions, and operating agreements, would
enable greater innovation and efficiency by allowing non-Federal entities a
greater role in performing work on these projects.

D. Water Infrastructure Resources

1. Authorize User Fee Collection and Retention under the WRRDA Section 5014 Pilot
Program and Recreation User Fees for Operation and Maintenance of Public
Facilities

 Currently, neither the Federal Government nor non-Federal service providers


have authority to impose user fees under the water infrastructure pilot program
authorized under Section 5014 of the Water Resources Reform and
Development Act (WRRDA) of 2014. When user fees are permitted, they are
sent to Treasury once collected, not returned to operate and maintain the site
from which they were generated.
 Without a dedicated revenue source, innovative partnerships are nearly
impossible to execute because third parties would be subject to appropriation
risk. This risk makes transactions uneconomical and highly unlikely to close.
Aging infrastructure at USACE-managed recreation sites is in need of
significant repair and rehabilitation, and annual USACE appropriations have
not been sufficient to address long-term operation and maintenance needs and
safety concerns.
 Authorizing the Federal Government and third party service providers to
impose and retain fees under WRRDA to use or defray costs associated with
carrying out a project would enable effective infrastructure partnerships. This
proposal would limit application to no more than ten projects and would
specify that the respective non-Federal interests indemnify and hold the
Federal Government harmless as a result of non-Federal actions, including that
the Federal Government assumes no responsibility for costs of said non-
Federal actions. Amending the law (16 U.S.C. 460d-3) to provide USACE the
authority to retain recreation user fees generated at USACE-managed
recreation sites and facilities would enable USACE to address the backlog of
infrastructure, public safety and visitor use management needs at sites where
user fees are collected.

2. Expand U.S. Army Corps of Engineers’ Authority to Engage in Long-term Contracts

 Current law generally restricts the award of multi-year contracts to a period of


no more than five years.
 Infrastructure asset contracts typically are much longer than five years, and
therefore the cost and risk associated with five-year contracts creates a cost
and resource prohibitive barrier to successful transactions.

29
 Extending the contract period to allow the Secretary of the Army to enter into
contracts for a period up to 50 years would enable USACE to enter into long-
term contracts that encompass the full life-cycle management of infrastructure
assets in the program (Section 5014 of WRRDA). This amendment would
specify that the respective non-Federal interests indemnify and hold the
Federal Government harmless as a result of non-Federal actions, including that
the Federal Government assumes no responsibility for costs of said non-
Federal actions.

3. Authorize Commercial Operation and Maintenance Activities at Hydropower


Facilities

 Current law defines operation and maintenance activities at hydropower


facilities undertaken by Civil Works personnel as of the date of enactment of
the Water Resources Development Act of 1990 as inherently governmental and
not commercial activities. (Section 314 of the Water Resources Development Act
of 1990; 33 U.S.C. 2321).
 This designation creates unnecessary bureaucracy and restricts open
competition that leads to excess costs for operations that can easily be done at a
lower cost and more efficiently.
 Amending the law to restore the authority of the Secretary of the Army to
determine whether operation and maintenance functions at hydropower
facilities on USACE projects are commercial activities and appropriate for
performance by non-Federal entities would increase the opportunity for open
competition and lead to more efficient operations and maintenance.

4. Deauthorize Certain Federal Civil Works Projects

 Currently, all USACE projects remain authorized in perpetuity. This includes


completed projects that are under USACE control but are approaching the end
of their service life, as well as projects that were built by USACE but are
operated and maintained by non-Federal entities. Extensive regulatory and
statutory compliance provisions apply to non-Federal sponsors associated with
USACE projects, including Section 14 of the Rivers and Harbors Act of 1899, as
amended (33 U.S.C. 408, commonly referred to as “Section 408”).
 These provisions can make local alterations to federally constructed projects
expensive and difficult, as even simple modifications to a Federal project by an
applicant trigger a Section 408 review, which increases the costs to both the
Government and the applicant.
 Amending the law to establish a streamlined deauthorization process that
allows for those USACE projects approaching the end of their service life and for
those projects operated and maintained by non-Federal interests that do not
require Federal oversight would release Federal and non-Federal resources to
be used for other purposes.

5. Expand Authority for Acceptance of Contributed and Advanced Funds

30
 A non-Federal sponsor can provide non-Federal funds to the Federal
Government through contributed and advanced funds, to advance investments
in infrastructure. However, under current law, the process to accept
contributed and advanced funds is protracted and limited by several factors.
 Projects therefore suffer years of delay, unable to take full benefit of a willing
sponsor to provide non-Federal funds.
 Amending the law (33 U.S.C. 701h) to expand authority for the acceptance of
contributed funds even if no Federal funds have been appropriated for the
authorized project, changing individual notifications to an annual reporting
requirement, and expanding applicability of advanced funds authority to all
authorized water resources development studies and projects would increase
non-Federal spending and expedite project execution.

6. Amend Water Resources Development Act to Allow for Waiver of Cost Limits

 Current law provides a maximum total cost for congressionally authorized


projects.
 Projects that exceed the cost limitation (Section 902 of the Water Resources
Development Act of 1986) require authorization by Congress to raise the
maximum total project cost, which can add significant delays in delivering
infrastructure projects.
 Amending the law to allow the maximum total cost limitation to be waived
upon the recommendation of the Secretary of the Army would provide
flexibility to avoid delays in delivering infrastructure projects.

III. VETERANS AFFAIRS

The following provisions would provide flexibility to the Department of Veterans


Affairs (VA) to use the value of its existing assets to provide our Nation’s veterans the
state-of-the-art facilities they deserve. The VA has a nationwide physical footprint
that includes aging facilities. While the physical assets owned by the VA are growing
outdated, the underlying property values continue to increase.

A. Provide VA Real Property Flexibilities

 Authorize VA to retain proceeds from sales of properties and exchange existing


facilities for construction of new facilities. Under current law, the VA cannot
retain the proceeds from sales of its properties, nor can the VA exchange its
existing facilities for the construction of new facilities. This hinders the VA’s
ability to make needed capital improvements, including new construction and
renovations. Authorizing the VA to retain proceeds from sales of its properties
and exchange its existing facilities or land for new construction would provide
the VA flexibility to better fulfill its mission, including making capital
improvements for new construction and renovations and for funding lease or
service costs in a facility.

31
 Authorize pilot program for VA to exchange land or facilities for lease of space in
multi-tenant facilities. Congress should create a pilot program, for up to five
projects, to allow the VA to exchange existing VA land or facilities for a lease of
space in a resulting private facility built on the former VA land. The VA-
occupied space would be built to the same commercial standards as the
remainder of the facility and could be in a stand-alone building or part of
another building. The private sector financing could not be based on the full
faith and credit of the U.S. Government or guaranteed U.S. Government
tenancy. The lease term after credits would be a maximum of seven years, and
any future lease or extension after the initial term also would be limited to
seven years. The lease and service rates during the credit timeframe and any
subsequent lease term would be at market or less. The explicit dollar amount of
termination (e.g., one year of rent payments) would be required to be included
in the agreement, and VA would budget rent and termination in accordance
with OMB Circular A-11. The lease would be structured to assure that VA had
exit privileges, and that VA would have an exclusive right, but not the
obligation, to renew or extend the term of the lease.
 Increase the threshold above which VA is require to obtain congressional
authorization for leases. Current law requires VA to obtain congressional
authorization for any lease above $1 million in annual costs. This differs from
the GSA prospectus threshold established under title 40 of the United States
Code. The GSA prospectus currently carries a threshold of $3.095 million and is
reevaluated periodically. These differing thresholds require the VA to seek
authorization for more leases. Increasing the authorization threshold for VA
major medical leases (38 U.S.C. 8104) from the current threshold of $1 million
in annual costs to the current GSA prospectus threshold which is $3.095 million
and updated periodically would reduce the number of VA authorizations and
align the authorization levels across the two programs.

IV. LAND REVITALIZATION (BROWNFIELD/SUPERFUND REFORM)

The below provisions would expand funding eligibility for revitalization projects and
establish tools to manage and address legal and financial risks. These provisions
would incentivize the development and dissemination of strong infrastructure risk
mitigation and asset management standards to accelerate the desired
transformational shifts for the public good—increases in revenue generation, risk
allocation to the parties best equipped to mitigate concerns, and greater attention to
maintenance and innovative design.

A. Create a Superfund Revolving Loan Fund and Grant Program and Authorize
National Priorities List Sites to be Eligible for Brownfield Grants

 Currently, the Brownfield program has a revolving loan/grant fund, but under
CERCLA Sections 101(39)(B) and 101(41)(C), Superfund sites are not eligible for
the program. National Priorities List (NPL) sites currently are not eligible for
Brownfield grants.

32
 Therefore, low interest loan funds are not available to clean up Superfund sites
and because NPL sites cannot access Brownfield grants, they cannot fund any
development unrelated to the response action.
 Amending the Small Business Liability Relief and Brownfields Revitalization
Act to include a Superfund revolving fund would facilitate new investment into
Superfund cleanup and reuse and would provide non-liable third parties a low
interest source of funds to perform removals, remedial design, remedial action
and long-term stewardship. Amending the law (CERCLA Section 101(40)) to
allow NPL sites or portions thereof to be eligible for Brownfield grants at EPA’s
discretion would make funds available to eligible entities to conduct
assessments, complete cleanups, and implement remedy enhancements to
accommodate development and perform long-term stewardship. This
proposal would include areas of the NPL site that are not related to the response
action; areas that can be parceled out from the NPL response action; areas
where the NPL response action is complete but the site has not been delisted
yet; or areas where the NPL response action is complete but the facility is still
subject to orders or consent decrees under CERCLA. This would be a new
Brownfields grant program targeted to Superfund sites.

B. Provide Liability Relief for States and Municipalities Acquiring Contaminated


Property through Actions as Sovereign Governments

 Currently, State and local governments may be exempt from CERCLA liability as
an “owner or operator” if they acquire ownership or control of contaminated
property involuntarily through bankruptcy, tax delinquency, abandonment, or
other circumstances under which the State or local government involuntarily
acquires title by virtue of its function as a sovereign government.
 However, confusion exists regarding the meaning of “a unit of State or local
government,” “involuntary acquisition,” and “acquires title by virtue of its
function as sovereign,” which inhibits State and local governments from
becoming full partners in the cleanup and reuse of Superfund sites.
 Clarifying and expanding the current liability exemption (CERCLA Section
101(20)(D)) to afford State and local governments an exemption from liability
for all property acquisitions undertaken by virtue of their sovereign function
would encourage these entities to become full partners in the cleanup and reuse
of Superfund sites. Additionally, these changes would allow more State and
local governments to be eligible for grants and to acquire property without fear
of liability. Such relief from liability would be conditioned upon State and local
governments not contributing to the contamination and meeting the
obligations imposed on Bona Fide Prospective Purchasers (BFPPs) in Section
101(40)(C)-(G), including exercising appropriate care with respect to releases
of hazardous substances at the facility.

C. Provide EPA Express Settlement Authority to Enter into Administrative


Agreements

33
 Currently, CERCLA does not provide express authority for EPA to enter into
certain administrative settlement agreements to clean up and reuse sites. EPA
does not have express authority to settle with BFPPs or other third parties who
may be subject to a statutory defense or exemption or to settle administratively
with a potentially responsible party who is willing to perform remedial
action. CERCLA (Section 122(a)) provides the President with authority to enter
into an agreement with any person to perform a response action when the
President determines the action will be done properly. CERCLA further requires
that when EPA enters into a settlement for a remedial action with a potentially
responsible party, the settlement must be approved by the Attorney General
and entered into the United States District Court as a consent decree.
 CERCLA limitations hinder the cleanup and reuse of Superfund sites and
contribute to delays in cleanups due to negotiations.
 Amending the law to provide EPA with express settlement authority to enter
into administrative agreements with BFPPs and other statutorily protected
parties and to enter into administrative agreements with any party to perform
remedial action in appropriate circumstances (e.g., partial, early remedial
action) would promote and expedite the cleanup and reuse of Superfund sites.

D. Integrate Cleanup, Infrastructure and Long-term Stewardship Needs by


Creating Flexibility in Funding and Execution Requirements

 CERCLA and appropriations laws restrict EPA’s ability to creatively integrate


cleanup, rebuilding infrastructure, and long-term stewardship. Additionally,
EPA is subject to a number of restrictions on its ability incorporate
infrastructure needs into cleanup design and implementation, particularly with
respect to coordinating funding of such activities.
 These restrictions prevent EPA from incorporating infrastructure needs into
cleanup design and implementation.
 Removing these restrictions for infrastructure projects that could easily be
integrated with the cleanup work and funded by a third party, would enable EPA
to better incorporate infrastructure needs (e.g., pipelines, power lines) into
cleanup design and implementation and would promote site reuse.

34
PART 3—INFRASTRUCTURE PERMITTING IMPROVEMENT

I. FEDERAL ROLE

The below provisions would protect the environment while at the same time
delivering projects in a less costly and more time effective manner by:
 creating a new, expedited structure for environmental reviews;
 delegating more decision-making to States and enhancing coordination
between State and Federal reviews; and
 authorizing pilot programs through which agencies may experiment with
innovative approaches to environmental reviews while enhancing
environmental protections.

A. Establishing a “One Agency, One Decision” Environmental Review Structure

1. Protect the Environment through a Structure that Establishes Firm Deadlines to


Complete Environmental Reviews and Permits

 Under current law, project sponsors of infrastructure projects must navigate


environmental reviews under the National Environmental Policy Act (NEPA)
and permitting processes with multiple Federal agencies with separate
decision-making authority and often counter-viewpoints. These many hoops
affect the ability of project sponsors to construct projects in a timely and cost
effective manner.
 This creates inefficiencies in project environmental protection, review and
permitting decisions, which delays infrastructure investments, increases
project costs, generates uncertainty, and prevents the American people from
receiving the benefits of improved infrastructure and environmental
protections in a timely manner.
 This proposal would establish a firm deadline of 21 months for lead agencies to
complete their environmental reviews through the issuance of a Finding of No
Significant Impact (FONSI) or Record of Decision (ROD), as appropriate.
 Additionally, the proposal would establish a firm deadline of 3 months after the
lead agency’s FONSI or ROD for Federal agencies to make decisions with respect
to the necessary permits. (This 3-month deadline also would apply to any
permits issued by State agencies under Federal law pursuant to delegations of
authority from a Federal oversight agency where such permits are a
prerequisite to the completion of a Federal agency’s ability to issue a permit.)
Appropriate enforcement mechanisms would be established to ensure that
permit decisions are issued.
B. Reducing Inefficiencies in Environmental Reviews

1. Require a Single Environmental Review Document and a Single Record of Decision


Coordinated by the Lead Agency

35
 Currently, Federal NEPA reviews are conducted by the Federal agencies with
jurisdiction over the same project. Agencies are encouraged, but not required,
to prepare joint analyses. Requiring joint analyses can reduce the potential for
delay caused by separate analyses.
 When not coordinated, these reviews can be duplicative and difficult for a
project sponsor to navigate. Decisions are not issued in the same time frame
and frequently are spread out over long periods of time. This additional time
can add months, or even years, to the environmental review process, with little
benefit to the environment.
 Requiring the lead Federal agency under NEPA to develop a single Federal
environmental review document to be utilized by all agencies, and a single ROD
to be signed by the lead Federal agency and all cooperating agencies, would
reduce duplication and create a more efficient, timely review process.

2. Clarify that Alternatives Outside of the Scope of an Agency’s Authority or Applicant’s


Capability Are Not Feasible Alternatives

 The heart of the NEPA process is the evaluation of alternatives. The


development, analysis, and weighing of alternatives serves to ensure that
Federal officials make informed decisions.
 However, an agency should not be required to consider alternatives that are
outside its authority or outside the capability of the applicant. Such
alternatives are not feasible and do not need to be considered in an
environmental review.
 Clarifying that alternatives outside the scope of an agency’s authority or an
applicant’s capability are not feasible alternatives for purposes of NEPA would
allow agencies and applicants to focus their resources and analyses on those
alternatives that are actually legally, technically, and economically feasible.

3. Direct the Council on Environmental Quality to Issue Regulations to Streamline the


NEPA Process

 Council on Environmental Quality (CEQ) regulations and guidance provide an


important basis for the implementation of NEPA. The environmental review
process under NEPA as it exists today is lengthy, inefficient, and costly.
 CEQ’s regulations were issued in 1978, before the advent of the Internet, and
have been subject to only one revision since then.
 Requiring CEQ to revise its regulations to streamline NEPA would reduce the
time and costs associated with the NEPA process and would increase efficiency,
predictability, and transparency in environmental reviews.

4. Eliminate Redundancy in EPA Reviews of Environmental Impact Statements under


Section 309 of the Clean Air Act

 Currently, Section 309 of the Clean Air Act requires that EPA review and publish
comments on most Environmental Impact Statements (EISs) (42 U.S.C. 4332).

36
Under this authority, EPA publishes comments on draft and final EISs. EPA also
provides a rating for EISs. In addition to its responsibility under Section 309,
EPA has a separate regulatory responsibility to review and comment on EISs on
matters within its jurisdiction and typically would be included as a cooperating
agency for areas within its technical expertise.
 The extra review under Section 309 adds a step to the environmental review
process that can cause delays without increasing protection to the
environment. Issues are sometimes raised late in the process or go beyond the
bounds of EPA’s subject matter expertise. Lead Federal agencies must take
time to respond to EPA’s additional comments in the Section 309 review, even
if the comments are outside of EPA’s special expertise. This review is no longer
necessary, given that Federal agencies have gained significant NEPA experience
since this law was enacted and because EPA has other authority to review and
comment on matters within its jurisdiction.
 Eliminating EPA’s additional review and assessment of EISs would remove
duplication and make the environmental review process more efficient. This
change would not eliminate EPA’s regulatory responsibilities to comment
during the development of EISs on matters within EPA’s jurisdiction or EPA’s
responsibilities to collect and publish EISs. It also would not prevent EPA from
providing technical assistance to the lead or other cooperating agencies upon
request.

5. Focus the Scope of Federal Resource Agency NEPA Analysis on Areas of Special
Expertise or Jurisdiction

 Currently, disagreements often occur regarding the proper scope of NEPA


review, particularly a resource agency’s review for a large or complex project.
Federal agencies sometimes provide comments or raise objections to issues
beyond the scope of their areas of special expertise or jurisdiction.
 These objections and comments create confusion for the public and result in
untimely decisions and additional workload.
 Focusing Federal resource agencies’ authority to comment on portions of the
NEPA analysis that are relevant to their areas of special expertise or jurisdiction
would maximize the effectiveness of agency reviews and streamline project
delivery.

6. Reduce Duplication and Increase Flexibility in Establishing and Using Categorical


Exclusions

 Currently, each Federal agency establishes its own categorical exclusions (CEs)
by developing a record to substantiate that an activity would not result in
significant environmental impacts. All categorical exclusions that a Federal
agency proposes to establish or change are reviewed and approved by CEQ.
 Even when a CE has been substantiated by a Federal agency and approved by
CEQ, it may not be used by another Federal agency without a separate
substantiation and approval process to incorporate the CE into the other

37
Federal agency’s NEPA procedures. A Federal agency also may not change its
internal documentation requirements related to CEs, such as moving a
“documented” CE to the “undocumented” list, even if experience shows that
documentation is no longer needed.
 Authorizing any Federal agency to use a CE that has been established by
another Federal agency and identifying documented CEs that can be moved to
an agency’s undocumented CE list without undergoing the CE substantiation
and approval process would reduce duplication and unnecessary environmental
analysis for actions that do not create a significant environmental impact. Each
agency would track and catalogue its use of another agency’s CEs under this
provision.

7. More Effectively Address Environmental Impacts by Allowing Design-Build


Contractors for Highway Projects to Conduct Final Design Activities before NEPA Is
Complete

 Under current law, a design-build contractor for a Federal-aid highway project


is not authorized to commence final design activities until after the conclusion
of the NEPA process (23 U.S.C. 112(b)(3)).
 This restriction diminishes the flexibility afforded with the design-build
procurement method, because States are not permitted to allow designers to
proceed with final design activities with their own funds under the traditional
design-bid-build method.
 Allowing design-build contractors to conduct final design activities would
facilitate better environmental reviews in conjunction with the design of
projects and would facilitate more efficient and more effective efforts to
address environmental impacts. The lead Federal agency would continue to
conduct an independent review of the environmental documents and prohibit
the agency from taking any action that would prevent the objective
consideration of alternatives.

8. Curtail Costs by Allowing for Advance Acquisition and Preservation of Rail Rights-
of-Way before NEPA Is Complete

 Currently, real property generally cannot be acquired for rail rights-of-way


prior to the completion of the NEPA environmental review process.
 While project sponsors might have an opportunity to purchase better and less
expensive rights-of-way in advance, the lack of clear statutory direction
impedes preservation of rail rights-of-way in advance of project approval.
 Allowing the advance property acquisition and preservation of rail corridors for
rail projects would help control costs and improve project delivery. Right-of-
way purchase still would be eligible for Federal funding only if used for a
project selected through the NEPA process. The risk of bias in the evaluation of
alternatives under these circumstances would be minimal, because project
sponsors would be able to recoup the value of property if a different alternative
ultimately was selected.

38
9. Enhance Integration of Transportation Planning and NEPA by Removing an
Unneeded Concurrence Point for Using Transportation Planning Documents and
Decisions in NEPA

 Under current law, lead Federal agencies have been encouraged to adopt or
incorporate by reference relevant documents and decisions into their NEPA
documents. This includes documents from the transportation planning
process. The transportation planning process includes robust study and public
engagement to develop transportation plans for metropolitan areas. In the
Moving Ahead for Progress in the 21st Century Act (MAP-21), Congress
formalized the practice of incorporating transportation planning documents
but added a new requirement that cooperating agencies had to concur (23 U.S.C.
168(d)).
 Concurrence for incorporating transportation planning documents and
decisions was not previously required and is not required for the adoption of
other documentation. The transportation planning documents already undergo
review and consideration by agencies and the public during plan development.
The additional concurrence point adds an unnecessary step that impedes
efficient environmental review and the integration of the planning and
environmental review process. It also can result in substantial duplication of
work, if a cooperating agency does not concur in the incorporation of
documentation from planning.
 Eliminating the requirement for concurrence by a cooperating agency would
reduce duplication and delay, and would facilitate the integration of the NEPA
process with the transportation planning process.

10. Remove Duplication in the Review Process for Mitigation Banking by Eliminating
the Interagency Review Team

 The 2008 Mitigation Rule that USACE and EPA jointly promulgated includes
specified timelines for various tasks associated with the approval and oversight
of mitigation banks. The Mitigation Rule provides an opportunity for public
and agency review and comment on mitigation banks during the approval
process. In addition to this review, the Mitigation Rule requires a second
review by an interagency review team, consisting of reviewing agencies, Tribal
nations, and the mitigation banking sponsor.
 Approval timelines often are extended beyond those specified in the Mitigation
Rule, due to protracted consultation among the interagency review team. The
final approval of a mitigation bank often is delayed because of the time it takes
to resolve disagreements among the entities participating in the second review.
 Removing the second review would enhance the efficiency of the mitigation
bank approval time frames. The members of the interagency review team
would still have an opportunity to review and comment through the public
participation process required in the Mitigation Rule.

39
11. Authorize All Lead Federal Agencies for Infrastructure Projects to Opt into Highway
and Transit Streamlining Procedures

 Highway and transit projects currently have specific statutory authority that
promotes efficiencies in the environmental review process for their projects (23
U.S.C. 139). This authority promotes efficiency without changing any
substantive environmental laws.
 However, these benefits are limited because they do not apply to other types of
infrastructure projects.
 Amending the current law to allow other lead Federal agencies to opt into these
provisions could make environmental reviews on other infrastructure projects
more efficient. This option would not apply to projects that are eligible under
FAST 41 because they already have separate streamlining provisions.

12. Increase Efficiency by Expediting Certain Small Telecommunications Equipment in


NEPA and the National Historic Preservation Act

 Current law requires that wireless deployers comply with both NEPA and the
National Historic Preservation Act (NHPA) for small cells and Wi-Fi
attachments in the same way that they obtain permits for large towers.
 Small cells and Wi-Fi attachments do not have an environmental footprint, nor
do they disturb the environment or historic property. However, despite this
lack of impact, small cells and Wi-Fi attachments typically go through the
same level of analysis and review under NEPA and the NHPA, which needlessly
adds both delays and costs to the process.
 Amending the law to expedite small cells and Wi-Fi attachments in NEPA and
the NHPA would eliminate unnecessary reviews without adversely affecting the
environment.

13. Create Incentives for Enhanced Mitigation

 Current environmental laws focus primarily on adverse environmental impacts


of infrastructure projects, without also recognizing their potential
environmental benefits.
 Opportunities for enhancing mitigation or environmentally friendly designs
often are lost, because they delay project development without providing any
benefit to the project sponsor.
 Establishing procedures that expedite environmental or permitting reviews for
projects that enhance the environment through mitigation, design, or other
means would provide incentives for project sponsors to propose more
environmentally beneficial projects. This would streamline the environmental
and permitting review process for those projects that demonstrate an
improvement to the environment.

14. Modify the Federal Power Act and Other Laws to Prohibit the Ability of Federal
Agencies to Intervene in FERC Proceedings

40
 Under current FERC policy and regulations, agencies that participate as
cooperating agencies in FERC’s preparation of NEPA documents cannot also
intervene in the FERC licensing proceeding. The rationale for FERC’s policy is
that cooperating agency staff will necessarily engage in off-the-record
communications with FERC staff concerning the merits of issues in the
proceeding. If the agency is subsequently allowed to become an intervenor in
the licensing proceeding, the agency would then have access to information
that is not available to other parties, in violation of the prohibition on ex parte
communications in both FERC’s rules and in the Administrative Procedure Act.
 FERC’s rules force Federal agencies to choose either to waive their right to
intervene in the proceeding or their right to participate, upon request, as a
cooperating agency in FERC’s preparation of an environmental document. By
choosing not to participate as a cooperating agency, FERC loses the benefit of
the agency’s technical expertise on important environmental issues, thus
inhibiting the identification and resolution of key issues early in the NEPA
process.
 Modifying the Federal Power Act and other laws to require Federal agencies,
upon request, to participate as a cooperating agency to a FERC NEPA review
would ensure that agencies fully participate in the preparation of FERC NEPA
documents. Agency participation as a cooperating agency, however, would not
impede that agency’s ability to file comments to the FERC docket for the
relevant proceeding nor impede the agency’s ability to defend any requested
conditions in court.

15. Authorize Federal Agencies to Accept Funding from Non-Federal Entities to Support
Environmental and Permitting Reviews

 Currently, some legal authority exists for project proponents to contribute


funds to Federal agencies to support such reviews and decisions. This includes
authority for public entities to support Federal agencies, State agencies, and
Indian tribes participating in environmental planning and review processes for
transportation projects (49 U.S.C. 307), as well as authority for USACE to accept
funds from non-Federal public entities to provide priority review of permit
applications (33 U.S.C. 2352). However, there is no universal authority to accept
funding from non-Federal entities for infrastructure projects.
 This limits the ability of Federal agencies to obtain additional resources to help
with the permitting and review process, thus causing further delays in project
development.
 Amending the law to provide broader authority for Federal agencies to accept
funds from non-Federal entities to support review of permit applications and
other environmental documents would provide additional resources to
streamline project delivery and would help defray the costs of the
environmental review. This provision would include appropriate controls for
potential conflicts of interest and would maintain the Federal agency’s
responsibility to conduct its review independently.

41
C. Protecting Clean Water with Greater Efficiency

1. Eliminate Redundancy, Duplication, and Inconsistency in the Application of Clean


Water Provisions

These provisions would make the following reforms to create greater efficiencies in
the application of clean water provisions:

a. Authorize Federal agencies to select and use nationwide permits without


additional USACE review. Currently, Federal agencies are required to submit
permit applications to USACE for some projects that meet nationwide permit
(NWP) requirements, including general and regional conditions. Federal
agencies employ staff who are environmental experts and review these
projects before submitting the application to determine whether they meet the
criteria for the applicable NWP. Eliminating the additional USACE review and
allowing Federal agencies to move forward on NWP projects, subject to permit
conditions, would streamline the process and allow USACE to focus on projects
that do not qualify for NWPs, which have greater environmental impacts.
USACE would retain the right to reinitiate its review for any agency that it finds
has incorrectly determined that NWP criteria were met.

b. Consolidate authority to make jurisdictional determinations for 404 permits.


Under current interpretation of the Clean Water Act, the EPA Administrator,
not the Secretary of the Army, has final authority to construe the jurisdictional
term “navigable waters” under Section 404 of the Clean Water Act. USACE has
decades of experience and expertise in jurisdictional matters, providing the
public approximately 59,000 written jurisdictional determinations per year.
Establishing the Secretary of the Army’s authority to make jurisdictional
determinations under the Clean Water Act would eliminate duplication of work
and streamline permit decisions. EPA and USACE would continue to coordinate
on rulemaking to ensure consistency in the definition of “waters of the U.S.”
under the Clean Water Act and to reconcile differences in determinations under
other sections of the Clean Water Act.

c. Eliminate duplicative oversight by removing EPA’s authority to veto a 404


permit under Section 404(c). The Secretary of the Army, acting through the
Chief of Engineers, has authority to grant permits for the discharge of dredged
or fill material under Section 404 of the Clean Water Act. EPA can exercise veto
authority prior to, during, and after permit decisions. The threat of the veto
creates significant uncertainty and delays permit decisions, because project
proponents and USACE address perceived concerns to avoid elevation or veto.
Removing EPA’s authority to veto a 404 permit would make the permitting
process more efficient and predictable.

d. Allow use of one NEPA document for both Section 404 and Section 408 actions.
Section 408 authorizes the Secretary of the Army to grant permission for the

42
alteration, occupation, or use of a USACE civil works project if the activity will
not be injurious to the public interest and will not impair the usefulness of the
project (33 U.S.C. 408). To make this determination, Section 408 requires a very
similar environmental review to the review required for a Section 404 permit.
For actions where both Sections 404 and 408 apply, two independent
environmental reviews are required, creating unnecessary duplication of work
and delays in issuing permitting decisions.

e. Eliminate duplication in environmental documentation for authorized USACE


projects pursued by non-Federal interests. Under current law, if a non-Federal
entity intends to implement an authorized USACE civil works project without
an executed project partnership agreement, the non-Federal entity would need
a permit from the Department of the Army prior to construction (33 U.S.C. 403
and 33 U.S.C. 1344). To authorize the same civil works project, the USACE also
would prepare an environmental review and compliance document. Allowing
the non-Federal interest to use the completed USACE environmental
compliance documentation and decision (e.g., ROD or FONSI) as the
environmental review for the Federal permit decision would reduce duplication
without removing environmental protections.

2. Clarify Time Frames and Reduce Delays for Section 401 Certification Decisions

 Current law requires receipt of a State Water Quality Certification (Section 401
Certification) prior to USACE issuing a Department of the Army (DA) permit
(Section 404 and Section 10) decision. Under current law, a State is given a
period not to exceed one year to issue its Water Quality Certification, or the
requirement is waived.
 In spite of the statutory time frame, States increasingly do not issue permits
within the applicable time frames, or they require applicants to re-file prior to
the one-year lapse, which produces a loop of repeated lack of issuance and re-
filing.
 Amending the Clean Water Act to change the time period for issuance of a State
401 Certification by addressing the time periods for making a completeness
determination and the time for a State decision would reduce this delay.

3. Stabilize Utility Investments by Lengthening the Term of a National Pollutant


Discharge Elimination System Permit and Providing for Automatic Renewals

 Currently, the Clean Water Act places a five-year limitation on the term of
permits granted.
 This limitation serves as a disincentive to public and private investments in
investor-owned and publicly owned utilities when major investments typically
are financed over 20 to 30 years. Moreover, administrative resources in
granting permit renewals can significantly impact the timeliness of permit
renewal requests.

43
 Lengthening the permit time limit from five years to fifteen years and
providing for automatic renewals of such permits, if the water quality needs do
not require more stringent permit limits, would bring more stability to such
investments.

D. Reducing Inefficiencies in the Magnuson Stevens Act

1. Require Timelines to be Met under the Magnuson Stevens Act or Allow Agency to
Proceed with Action

 The Magnuson Stevens Act allows for both an abbreviated consultation process
(National Marine Fisheries Service (NMFS) must respond within 30 days) and
an expanded consultation process (NMFS must respond within 60 days) when
evaluating effects to Essential Fish Habitat.
 Even with these relatively short time frames, consultations tend to take much
longer to complete, and thus impact the delivery of infrastructure projects.
 Requiring NMFS to respond to all consultations within 30 days in all cases
(unless a 30-day request for extension is received from NMFS and approved by
the action agency) would improve time frames and eliminate delays. If no
response were received from NMFS within the required time frame, the action
agency could then move to final agency action.

E. Reducing Inefficiencies in Protecting Clean Air

1. Eliminate Confusion by Clarifying that Metropolitan Planning Organizations Need


only Conform to the Most Recent National Ambient Air Quality Standard

 Currently, the Clean Air Act requires EPA to establish National Ambient Air
Quality Standards (NAAQS) for certain pollutants. It also requires EPA to
periodically review and, if necessary, update these standards.
 This creates a problem every time EPA promulgates newly updated NAAQS
before prior standards are revoked. State DOTs and metropolitan planning
organizations (MPOs) may be required to demonstrate conformity to both the
old and new standards for the same pollutant, creating redundancy and
uncertainty, and causing State DOTs and MPOs to spend their limited resources
unnecessarily.
 Amending the Clean Air Act to clarify that conformity requirements apply only
to the latest NAAQS for the same pollutant would avoid this confusion and
reduce legal challenges.

2. Reduce Uncertainty by Establishing Motor Vehicle Emissions Budgets before


Requiring Initial Transportation Conformity Determinations for Newly Designated
Areas

 Currently, the Clean Air Act requires a newly designated area to comply with
conformity requirements one year after the effective date of the final

44
nonattainment designation (42 U.S.C. 7506(c)). Conformity typically is
demonstrated by showing that an area’s transportation plans will not exceed
the motor vehicle emissions budget established for that area.
 This creates a problem for newly designated areas because the emissions
budget usually takes longer than a year to establish and for EPA to approve.
Therefore, in order to demonstrate conformity, MPOs in newly designated
areas have to use other less suitable tests, such as “an interim emissions test”
or a test based on emissions budgets developed for a previous standard for the
same pollutant. These requirements have created confusion and uncertainty.
 Allowing transportation conformity to apply one year after EPA approves or
finds the emissions budgets adequate for conformity purposes would eliminate
confusion and give MPOs certainty in meeting Federal requirements.

F. Reducing Inefficiencies in Preserving Publicly Owned Land and Historic


Properties

1. Remove Overlapping DOI, USDA, and HUD Reviews from Individual Section 4(f)
Evaluations

 Under current law, DOT is prohibited from using parklands or historic sites
unless it determines that there is no other prudent and feasible alternative.
Current law requires consultation with DOI, USDA, and the Department of
Housing and Urban Development (HUD) in making these determinations. The
FHWA/FTA implementing regulations for Section 4(f) of the DOT Act (23 CFR
774.5) require Section 4(f) determinations to be sent to DOI, USDA, and HUD for
review and provide a minimum of 45 days for the agencies to comment.
Current law also provides for an additional 15-day period after the comment
deadline for DOI, USDA, and HUD to transmit comments before FHWA may
assume no objection (49 U.S.C. 303 and 23 U.S.C. 138).
 The DOI, USDA, and HUD reviews can delay project delivery even though the
review generally does not produce any changes in the determinations, because
the agencies have had little direct involvement in a project.
 Removing DOI, USDA, and HUD responsibilities to review individual Section
4(f) determinations would reduce delays in the project development process
while not reducing protections to parklands and historic sites.

2. Eliminate Duplicative Reviews of Historic Property Impacts for Transportation


Projects

 Under current law, potential impacts of transportation projects on historic sites


must undergo a review under both Section 106 of the NHPA and Section 4(f).
These two laws are different in approach (Section 4(f) results in a substantive
determination and Section 106 is a process resulting in an agreement), but both
are designed to protect the same historic resources. The FAST Act added an
optional process for historic preservation reviews to address this issue, but it

45
added new steps and concurrence points that do not exist in the current
regulatory process.
 Conducting two reviews to protect historic properties is redundant and creates
substantial additional work. It is also inconsistent with requirements for other
infrastructure projects, which only need to comply with Section 106. Because of
the additional concurrence points, the optional process included in the FAST
Act is a more cumbersome process and has not been used.
 Specifying that an action taken pursuant to a Section 106 agreement does not
constitute a “use” under Section 4(f), and therefore would not require a
different analysis, would reduce duplication and delay, without reducing
protections for the historic properties.

3. Eliminate Redundancy in Conversion Requirements When Land Purchased with


Land and Water Conservation Fund Money Is Impacted

 Currently, parks and other sites that have been the subject of Land and Water
grants of any type cannot be converted to other than public outdoor recreation
uses without approval of the NPS. This includes approval of equivalent
property to substitute for the converted area. This requirement applies to
infrastructure projects that might use parks or other recreational facilities that
were funded by Land and Water grants.
 Consulting with the NPS and obtaining its approval for equivalent substitution
property can be a lengthy process leading to delayed project delivery. The work
of the NPS often duplicates the work of the lead Federal agency in identifying
equivalent substitute property.
 Eliminating the requirement for the NPS approval in identifying and procuring
replacement property would eliminate duplicative work and speed project
delivery (including where authority has been delegated to States).

4. Reduce Uncertainty by Establishing Reclamation Title Transfer Authorization

 Currently, there is no blanket authorization for Bureau of Reclamation to


transfer title to certain federally owned facilities currently operated by non-
Federal partners, who are the primary beneficiaries. Congress provides title
transfer authority with respect to individual facilities.
 Obtaining authority from Congress to transfer title for each facility individually
is arduous and very time consuming, often taking several years. Delays in
obtaining title negatively impact the ability of non-Federal partners to obtain
private financing to perform required major rehabilitation and replacement
needs. As a result, entities may need to request funding from the Federal
Government to perform required work.
 Establishing new transfer authority in the Bureau of Reclamation would
streamline the process and reduce delays for executing title transfers. This also
would facilitate non-Federal partners’ ability to seek private financing for
major rehabilitation and replacement needs. Additionally, this would give non-
Federal partners greater flexibility in setting operating criteria.

46
5. Reduce Uncertainty by Authorizing the Secretary of the Interior to Review and Approve
Permits for Pipelines Crossing Lands Administered by the National Parks Service

 Current law delegates to the Secretary of the Interior authority to review and
approve rights-of-way across lands administered by the NPS, but only for
electric, water and communications facilities. For pipelines (natural gas and
oil) and facilities necessary for the production of energy, specific congressional
authorization is needed for each proposed project crossing one of these lands.
 Obtaining congressional approval for each pipeline crossing and facilities
necessary for the production of energy is time consuming and delays
construction of needed natural gas pipeline facilities. It also is inconsistent
with the process adopted for other types of facilities.
 Authorizing the Secretary of the Interior to approve rights-of-way for pipelines
and facilities necessary for the production of energy across NPS-administered
land in a manner identical to that for other facilities would reduce the delays
and uncertainties caused by requiring congressional approval.

II. DELEGATION TO STATES

These provisions will streamline and expand existing procedures to entrust


environmental review and permitting decisions to States. These provisions also
would help avoid duplication by facilitating reliance on State and local reviews and
documentation.

A. Expand Department of Transportation NEPA Assignment Program to Other


Agencies

 Using current authority, DOT has successfully assigned its NEPA


responsibilities to six States under certain conditions and contingent upon the
States signing a memorandum of understanding with the DOT.
 However, this authorization to assign responsibility is limited to FHWA and
FTA.
 Authorizing other agencies to assign NEPA responsibilities to States would
extend the benefit of this program to other types of infrastructure agencies and
projects, under requirements similar to those in the DOT NEPA assignment
program.

B. Allow States to Assume FHWA Responsibilities for Approval of Right-of-Way


Acquisitions

 Currently, there is no specific authorization for States to assume FHWA’s


responsibilities for approving right-of-way acquisition transactions. In
addition, FHWA regulations require States to obtain authorization before
proceeding with any real property acquisition using Federal-aid highway funds.

47
 Waiting for FHWA can delay the project delivery process for Federal review of
what has become a routine activity for States.
 Providing States with authority to assume some, or all, of FHWA’s
responsibilities for approval of right-of-way acquisitions (subject to the same
legal protections that currently apply to the right-of-way acquisition process)
would eliminate these delays. DOT would retain the right to terminate a
delegation if a State improperly carries out its responsibilities for approving
right-of-way acquisitions.

C. Broaden NEPA Assignment Program to Include Other Determinations

 Currently, the Surface Transportation Project Delivery Program (“NEPA


assignment program”) allows States to fully assume Federal responsibilities
under NEPA for highway and transit projects. However, it prohibits DOT from
assigning, and States from assuming responsibility for, any project-level
conformity determination required under the Clean Air Act for the same
projects (42 U.S.C. 7506). It also does not authorize States to assume
responsibilities for determinations regarding flood plain protection and noise
policies, which would affect determinations made by States during the
environmental review process (23 U.S.C. 109 and 327).
 This inconsistent treatment diminishes the effect of the NEPA assignment
program. It causes the environmental review process assumed by a State to be
interrupted or impacted by Federal approvals or determinations during an
environmental review that otherwise has been fully assumed by the State.
 Allowing DOT to assign, and States to assume, project-level transportation
conformity determinations and determinations regarding flood plain
protections and noise policies as part of the NEPA assignment program would
create a more efficient NEPA assignment program. It also would provide an
incentive for additional States to participate in the NEPA assignment program.
Consistent with the requirements of the NEPA assignment program, States
would need to demonstrate the technical capacity to make these
determinations. This provision would not change EPA’s responsibilities under
the Clean Air Act.

III. PILOT PROGRAMS

These provisions would create pilot programs to experiment with new ways to address
environmental impacts while delivering projects in a more timely and predictable
way.

A. Performance-Based Pilot

 This pilot program would experiment with using environmental performance


measures instead of an environmental review process to address
environmental impacts of an infrastructure project. Up to 10 projects would be

48
selected to participate in the pilot based on project size, national or regional
significance, and opportunities for environmental enhancements.
 The project sponsor for a selected project would agree to design its project to
meet performance standards and permitting parameters established by the lead
Federal agency. The lead Federal agency would develop these standards with
public input and in coordination with other cooperating Federal agencies. The
project sponsor’s agreement to meet the performance standards and
permitting parameters would be in lieu of complying with NEPA and relevant
permits or other authorizations.
 The performance standards would result in design elements and enhanced
mitigation that address the impacts of the project and meet permit
requirements. The pilot would support the goals and objectives of NEPA and
meet permit obligations without being constrained by its procedural
requirements. It would focus on good environmental outcomes rather than a
lengthy environmental review process.

B. Negotiated Mitigation Pilot

 This pilot program would experiment with negotiation of mitigation to address


environmental impacts of transportation projects.
 This pilot would authorize the Secretary of Transportation (or other
infrastructure agencies) to establish an alternative decision-making process in
lieu of NEPA, based on negotiated mitigation agreements and supporting
mitigation markets that address anticipated project impacts for a specific set of
projects.
 Negotiated mitigation strategies could include purchase of offsets, avoidance of
anticipated impacts, and in-lieu-fee dedicated to an advanced mitigation fund.
 This pilot also would establish conditions and limitations for the DOT authority
under this pilot.

IV. JUDICIAL REFORM

These provisions would reform judicial review standards for environmental reviews to
avoid protracted litigation and to make court decisions more consistent. These
provisions also would narrow the scope of judicial review by exempting certain
actions or issues from challenge.

A. Limit Injunctive Relief to Exceptional Circumstances

 Currently, a legal challenge to a project under NEPA can delay the start of a
project, due to the uncertainty it creates about whether the project will be able
to proceed.
 This creates unpredictability regarding time frames for projects, which at the
outset can discourage potential investors, and in the end can postpone the
public benefits of needed infrastructure projects.

49
 Limiting injunctive relief to exceptional circumstances would allow for
environmental concerns to be addressed without unduly delaying needed
infrastructure projects.

B. Revise Statute of Limitations for Federal Infrastructure Permits or Decisions


to 150 Days

 Currently, for many infrastructure projects, the statute of limitations allows


plaintiffs to file legal challenges to Federal permitting and authorization
decisions for up to six years after the decisions have been issued. In addition,
under the program in which States can substitute comparable State laws for
NEPA (“NEPA substitution program”), the statute of limitations is two years
(23 U.S.C. 330).
 Infrastructure projects require significant investment in time and resources.
Delays and uncertainty caused by legal challenges to environmental and
permitting decisions inhibit investment in projects and impede the delivery of
public benefits from improved infrastructure. These delays and uncertainties
are exacerbated by long statutes of limitations, creating uncertainty well after
decisions have been made.
 Establishing a uniform statute of limitations of 150 days for decisions and
permits on infrastructure projects would reduce uncertainty and prevent
substantial delays in project delivery, while still affording affected parties an
adequate opportunity to initiate legal challenges. A 150-day statute of
limitations would be consistent with the statute of limitations Congress already
has enacted for surface transportation projects. In addition, revising the
statute of limitations for the NEPA substitution program to 150 days would
remove a barrier to States using this program.

C. Provide Certainty in Claims on Currentness of Data in Environmental Reviews


and Permits

 Environmental reviews and permitting decisions require in-depth studies and


data. These reviews can be costly and time consuming. Project sponsors and
Federal agencies are expected to use current data in conducting their
environmental and permitting reviews.
 With projects spanning several years, a project sponsor may need to conduct
multiple studies to generate data on the same issue. While using complete and
up-to-date data is necessary to make an informed decision, litigation risk
should not be the primary driver in deciding whether to conduct a new study.
 Directing Federal agencies to establish guidelines regarding when new studies
and data are required would clarify requirements and create more certainty in
the NEPA process. Courts would be precluded from reviewing any claims based
on the currentness of data, so long as agencies were in compliance with their
established guidelines. In a case where agencies’ guidelines for the same data
conflict, the guidance for the lead agency would prevail.

50
PART 4—WORKFORCE DEVELOPMENT

These provisions are dedicated to the American workforce and to policies that will
help Americans secure stable, well-paying jobs. The American workforce is an
important national asset, and thus should be included in legislation aiming to
strengthen and invest in our country’s infrastructure.

Currently, there are almost seven million individuals looking for work and roughly six
million unfilled jobs. Past Federal policies have left too many Americans behind. This
Administration is committed to helping more individuals access affordable, relevant,
quality education and skills-development that leads to full-time work and long-term
careers. These provisions also will have the important benefit of helping more
companies find skilled workers to fill open jobs.

An infrastructure bill will generate new projects that directly increase employment in
the construction industry, as well as boost the demand for labor more broadly as
additional infrastructure investment spurs economic growth. The provisions outlined
below will ensure our country has enough skilled workers to perform not only existing
work but also fill the new jobs created by the bill.

I. ACCESS TO EDUCATION AND WORKFORCE DEVELOPMENT PROGRAMS

A. Expand Pell Grant Eligibility to High-Quality, Short-Term Programs

 The Federal Government spends tens of billions of dollars each year in grants
for postsecondary education. However, the vast majority of these funds are
available only to help pay for courses that meet certain time and/or length
requirements. This model is becoming outdated given the expansion of short-
term education and workforce development programs that teach relevant skills
and help individuals secure well-paying jobs. For example, Pell Grants are
generally available only to students who do not yet have a bachelor’s degree
and who are enrolled in institutions of higher education offering degree
programs of at least 600 clock hours or 15 weeks in length.
 Pell Grants are not available for individuals pursuing shorter-term
certifications, including persons who are in skilled trades and who are
achieving certifications as part of an apprenticeship program. The Workforce
Innovation and Opportunity Act (WIOA) can fund some of these types of
education, but its funding is broadly distributed across a variety of workforce
development efforts.
 Expanding Pell Grant eligibility to high-quality, short-term programs would
allow individuals to use Pell Grants to pay for short-term programs that lead to
a credential or certification in an in-demand field. There is no “one size fits
all” approach to postsecondary education. Rather, there are multiple pathways
to success for students, and Federal law should enable students to explore and
access these pathways. It is of utmost importance that, as Pell recipients are
given greater flexibility in spending grant dollars, measures are undertaken to

51
ensure students receive quality education. Additionally, efforts should be taken
to ensure high-quality, short-term courses and programs are available in fields
where there are shortages of qualified workers.

B. Reform Career and Technical Education

 Equipping Americans with the education needed to do the jobs available in our
modern economy does not just require changes to our postsecondary education
and workforce development policies; it requires changes to our secondary
education policies as well. One Federal program related to skills-development
and career readiness – the Carl D. Perkins Career and Technical Education
(CTE) program – is in dire need of reform. CTE funds are spread thinly and
support a broad, fragmented range of activities, many of which are unlikely to
improve student outcomes and are often not aligned to local workforce needs.
 Too often, CTE programs do not successfully prepare students for jobs in high-
demand fields or local industries. In the 2015-2016 school year, the most
common CTE field for secondary CTE concentrators – those who specialize in a
single CTE field – was arts and design, followed by business and health.
 Enacting a modified version of the Perkins CTE reauthorization bill passed by
the House in June 2017 (H.R. 2353) would ensure that more students in
America’s secondary and postsecondary institutions have access to high-
quality technical education that teaches them practical knowledge and skills
needed in today’s technology-driven economy. There are several important
opportunities to amend H.R. 2353 to improve the legislation and advance the
Administration’s goals. Needed amendments include:
o Directing the majority of funding to high schools to promote strategies such
as apprenticeship, work-based learning, and dual-enrollment.
o Authorizing activities to promote and expand apprenticeships.
o Increasing high-quality CTE programs in high schools by promoting STEM
CTE offerings and other offerings related to in-demand industry sectors
(determined using the WIOA definition as a starting point and expanded
based on input from the private sector) and requiring that they are
evidenced-based (as defined by the Every Student Succeeds Act).
o Allowing States to pool funds to support regional centers and consortia that
support multiple districts in partnership with local businesses and other
community stakeholders.
o Strengthening the bill’s emphasis on the use of evidence-based research.
o Authorizing funding for fast-track programs that prepare high school
graduates for jobs rebuilding America’s infrastructure.

C. Strengthen Ties to the Workforce for College Students

 The Federal Work Study program (FWS) currently is not well-suited or targeted
to support students pursuing career and technical education, especially for
low-income and low-skilled students seeking to enter or return to the
workforce quickly.

52
 FWS funds are disproportionately distributed to four-year non-profit and
flagship public institutions, leaving out quality two-year programs, many of
which have a uniquely strong focus on workplace readiness.
 Enacting FWS reforms to better distribute the aid to schools and students who
can most benefit would ensure that more participants obtain relevant
workplace experience, including by participating in an apprenticeship. This
could include:
o Revamping the funding formula to send funds to schools with a strong
record in enrolling Pell students and putting them on a pathway to success.
o Limiting eligibility to undergraduates.
o Using program dollars to fund career-related internships or expanding
apprenticeship and career pathway programs.

II. EMPOWERING WORKERS

A. Reform Licensing Requirements for Individuals Seeking a Job on an


Infrastructure Project

 In many cases, States accepting Federal funding to support infrastructure


projects do not allow workers with out-of-State skilled trade licenses to work
on those projects.
 Preventing out-of-State professionals from working on infrastructure projects
can: (1) reduce the speed of these projects, delaying the effect of the economic
benefit they provide; and (2) increase the cost of the projects by artificially
limiting the supply of professionals available to work on those projects. These
provisions also put Americans who live in rural States or other areas at a
disadvantage since they frequently need to relocate (often temporarily) in order
to secure work.
 Requiring that States accepting Federal funds for infrastructure projects accept
workers with out-of-State licenses to work on those projects would speed
project delivery, reduce project costs, and provide flexibility to workers with
out-of-State skilled trade licenses.

###