You are on page 1of 28

Revised: August 5, 1999

Snyder Langston

Mobile
Crane Safety
Manual

Policies
and
Procedures

Page 1
Revised: August 5, 1999

Purpose ............................................................................................................................................................................................1
Scope ................................................................................................................................................................................................3
Authorities .......................................................................................................................................................................................3
Responsibilities ................................................................................................................................................................................3
Snyder Langston ..........................................................................................................................................................................1
Subcontractor ..............................................................................................................................................................................4
Crane Surveyor............................................................................................................................................................................4
Crane Owner ...............................................................................................................................................................................4
Crane Operator ...........................................................................................................................................................................5
Crane Oiler..................................................................................................................................................................................5
Definitions........................................................................................................................................................................................5
Accessory Gear ............................................................................................................................................................................5
Anti Two-Blocking Device ...........................................................................................................................................................5
Below-the-Hook Lifting Device....................................................................................................................................................5
Certified Agent.............................................................................................................................................................................6
Certification of Crane Operators (CCO) .....................................................................................................................................6
Functional....................................................................................................................................................................................6
Jib ................................................................................................................................................................................................6
On-Rubber Pick and Carry..........................................................................................................................................................6
Rolling Outriggers .......................................................................................................................................................................6
Qualified Person..........................................................................................................................................................................6
Procedures .......................................................................................................................................................................................6
Bid Procedures ............................................................................................................................................................................6
Subcontractor Safety Start-up Meeting ........................................................................................................................................6
Crane Survey Procedure..............................................................................................................................................................7
Crane Safety Requirements............................................................................................................................................................8
Inspection of Crane Equipment .....................................................................................................................................................9
California Projects ......................................................................................................................................................................9
Other States .................................................................................................................................................................................9
Load Testing of Jibs and Rolling Outriggers..............................................................................................................................10
Anti Two-Block Devices................................................................................................................................................................10
Cranes manufactured after February 28, 1992..........................................................................................................................10
Cranes manufactured before February 28, 1992.......................................................................................................................10
Load Rating Charts ......................................................................................................................................................................10
Interpretation.............................................................................................................................................................................11
Example................................................................................................................................................................................11
Critical Lifts ..................................................................................................................................................................................11
Critical Lift Plan........................................................................................................................................................................11
Crane Suspended Work Platforms ..............................................................................................................................................12
Qualifications of Crane Operators and Surveyors .....................................................................................................................12
Intent ..............................................................................................................................................................................................13

Page 2
Revised: August 5, 1999

PURPOSE
The purpose of these policies and procedures is to provide a safe working environment for crane operators
and all site personnel. In addition, surveys of the crane equipment and the operation of the crane has
proven to be advantageous to the flow and expediency of work performed during any crane operation on
construction sites.

SCOPE
These crane procedures shall be followed on all Snyder Langston projects by all Snyder Langston
employees, subcontractors, subcontractor’s employees, crane rental companies, crane operators, crane
users, and any other persons, organizations, or contractors entering or operating crane equipment on any
Snyder Langston job site. These crane procedures will provide a method by which all cranes 14 1/2 ton
capacity or greater shall be surveyed. However, all cranes shall be operated in accordance with all
applicable regulations during use on Snyder Langston projects. Prior to use on all projects, each 14 1/2
ton capacity or greater crane shall be surveyed by a qualified person, designated by Snyder Langston.
Further, Snyder Langston may require any crane of any capacity to be subject to these requirements at its
discretion. The survey will include an inspection of the crane components, accessory gear, below the
hook lifting devices, the assembly and setup of the crane each time a crane enters the project. The
Surveyor shall review each crane operator’s credentials prior to allowing the crane to be operated.
Additionally, the surveyor shall monitor the crane operation and identify any procedures considered an
unsafe operating practice. These procedures should assist the subcontractor and crane company in
maintaining a safe working environment when cranes are used on Snyder Langston projects.

It should be recognized that it is not feasible to address every possible issue, situation, and circumstance
that may arise or be encountered on a project. Therefore, if there are conflicts or an unsafe condition that
occurs which is not addressed in this manual for a particular crane operation matter, the Snyder Langston
safety manager and Snyder Langston’s crane safety consultant shall be contacted immediately, prior to
commencement of the crane operation.

AUTHORITIES
The criteria and standards for the safe operation of cranes shall include the following:
1. Manufacturer’s recommendations and requirements
2. American National Standards Institute (ANSI)
3. American Society of Mechanical Engineers (ASME)
4. Occupational Safety and Health Administration (OSHA)
Note: Where the project is located in a state that has its own regulatory agency such a California’s Division of Occupational Safety and Health
Administration (Cal-OSHA), the crane equipment must meet the requirements of the state agency.

These criteria are the minimum standards that must be met in all crane operations on all Snyder Langston
projects. This crane safety procedure manual does not purport to restate all of these regulations, but
should be used for clarification and additional criteria to be adhered to while operating crane equipment
on Snyder Langston projects.

RESPONSIBILITIES

Snyder Langston
The Project Superintendent shall be responsible for scheduling of the surveyor 48 hours prior to the
arrival of each crane unit. The Project Superintendent has complete authority to cease any crane activity
or operation on the project which does not comply with this manual and these policies and procedures.
Based upon the information provided by the crane surveyor, the superintendent may also refuse to allow
any crane to proceed to operate until such time that the unsafe condition can be eliminated. Where a
crane operator declines to make a lift based on any safety concerns, Snyder Langston and its Project
Superintendent will provide full support to eliminate the unsafe condition. Upon notification of any

Page 3
Revised: August 5, 1999

safety deficiency, the Project Superintendent will discuss a plan of action with the surveyor, sub-
contractor and crane crew to eliminate the safety deficiency.

Subcontractor
The subcontractor shall be responsible for providing Snyder Langston’s Project Superintendent with the
scheduled crane arrival time, general crane information such as type, size, and owner, anticipated lifts,
and any critical lift plans a minimum of 72 hours prior to scheduled arrival date of the crane. Each
subcontractor of Snyder Langston shall comply with this crane safety manual and these policies and
procedures. The subcontractor shall be responsible for providing each crane owner and all operators with
the crane safety criteria prior to bidding and/or arrival on any Snyder Langston project. Prior to
scheduling a crane, the subcontractor shall provide Snyder Langston with a completed “Pre-Erection
Hazard Analysis” form with a plan of action for items requiring corrective measures. The subcontractor
shall ensure that each item requiring corrective measures are corrected prior to the arrival of the crane
equipment. The subcontractor shall ensure that the crane and its crew are working within the guidelines
set forth by the governing authorities and Snyder Langston at all times. Any delays or down time due to
the determination or correction of any crane safety deficiency shall be at the subcontractor’s expense.
The subcontractor shall ensure that the crane company has provided Snyder Langston’s management with
a “certificate of insurance” and acceptable endorsement naming Snyder Langston & the project owner &
the subcontractor as additional insured on its general liability coverage 24 hours prior to the arrival of any
crane equipment to the job site.

Crane Surveyor
Snyder Langston retains the surveyor as a third party, independent crane safety consultant who is a
qualified person. He or she will provide the Project Superintendent, subcontractor and safety manager
with the results and findings of each crane safety survey. The crane surveyor shall ensure that the
requirements of this crane safety manual are followed by the subcontractors, crane crews, and crane
owners. The crane surveyor may serve as the liaison between the crane users and the project
superintendent. Upon identification of any safety deficiency that can not be eliminated prior to
commencement of the crane work, the surveyor shall report the deficiency to the subcontractor’s foreman
along with recommended plan of action. The surveyor shall inform Snyder Langston’s Safety Manager,
Snyder Langston’s Project Superintendent, and the crane owner respectively if discrepancies are
identified during the survey process that may affect the safe operation of the crane. If an imminent
danger exists by continued operation the crane operation shall cease immediately and appropriate action
shall be taken consistent with the reporting procedures set forth in this document.

Crane Owner
Each crane owner shall comply with this crane safety manual and these policies and procedures. Crane
owners providing equipment that is operated and maintained by personnel under their employ shall be
responsible for the training and qualifications of the operator. The crane owner shall provide all required
documentation such as manufacturers load charts, manufacturer’s maintenance criteria, and proof of
safety certifications consistent with the state and/or federal requirements for inspection by the crane
surveyor, Snyder Langston, the Project Superintendent, and/or the subcontractor. Where a safety
deficiency or unsafe operation is found, the crane owner shall provide the subcontractor and/or Snyder
Langston with a proposed plan of action to eliminate the safety deficiency. Any delays due to operations
or equipment that are adverse to these requirements shall be at the crane owner’s expense. Crane owners
shall provide Snyder Langston’s management with a “certificate of insurance” and an acceptable
endorsement naming Snyder Langston & the project owner & the subcontractor as additional insured on
its general liability and excess coverage 24 hours prior to the arrival of any crane equipment to the job
site. Snyder Langston shall provide the crane owner with evidence of builder’s risk insurance upon
request. Further, the crane owner shall be provided with the following Snyder Langston crane safety
documents:
1. Mobile Crane Safety Manual
2. Pre-Erection Hazard Analysis forms

Page 4
Revised: August 5, 1999

3. Crane Operation Safety Survey forms


4. Crane Safety Survey Procedure Flow Chart
5. Crane Safety Survey Process Flow Chart
It is the responsibility of the crane owner to ensure that these procedures are read and understood prior to
submitting a bid or estimate to any subcontractor or Snyder Langston for crane work.

Crane Operator
Effective June 1, 2000, Snyder Langston requires all crane operators to be certified under the NCCO. or
an equivalent program that has been reviewed by an independent assessment service (e.g. Buros Institute)
accepted by the Snyder Langston’s Safety Manager. All crane operators shall be experienced, trained,
and qualified to operate the size of crane, type of crane, and type of work to be performed on the Snyder
Langston project. The operator shall provide proof of any training certificate or licenses possessed
attesting to his or her crane operation knowledge, skill, and experience for review by the surveyor or
Snyder Langston Management. Each crane operator shall comply with this crane safety manual and these
policies and procedures. The crane operator shall work directly with the crane surveyor and provide the
surveyor with the information required on all Snyder Langston crane survey forms. The crane operator
will work with the crane surveyor in an effort to correct any safety deficiencies found during the survey.
Any crane operator, who determines that a lift is unsafe to be performed, shall refuse to continue
operation of the crane with the full support of Snyder Langston in eliminating the safety deficiency.
Upon finding an unsafe condition, crane operator shall consult with the Snyder Langston superintendent
and/or the crane surveyor in order to create a safe plan of action.

Crane Oiler
An oiler shall not operate any crane equipment unless he possesses the qualifications of a bona fide crane
operator as defined above. This limitation does not include positioning of the crane during relocation,
assembly, or disassembly. Further, the oiler may operate the crane as required during routine
maintenance in the performance of his or her general duties. Any crane oiler, who determines that a lift is
unsafe to be performed, shall notify the operator immediately and consult with the Snyder Langston
superintendent and/or the crane surveyor in order to create a safe plan of action.

DEFINITIONS1

Accessory Gear
A secondary part of the crane or crane component which contributes to the overall function of the crane
which includes but is not limited to jibs, jib assemblies, outriggers, sheave assemblies, and counter
weights.

Anti Two-Blocking Device


A warning or damage prevention feature which alerts the operator before the load block or ball assembly
makes contact with upper boom sheave assembly2.

Below-the-Hook Lifting Device


Rigging used in conjunction with the crane to attach the load to be lifted to the crane hook assembly
which includes but is not limited to such items as wire rope slings, lifting beams, skookum blocks,
shackles, and web slings.

1
A complete list of definitions may be found in ANSI B30.5 § 0.2 and in the state or federal O.S.H.A. standards.
2
A crane lifting personnel on a suspended work platform shall be equipped with a positive acting anti two-block
device that prevents damage to crane components.
Page 5
Revised: August 5, 1999

Certified Agent
The manufacturer, or a person who is currently registered as a professional civil, mechanical, or structural
engineer by the state in which the Snyder Langston project is located and is knowledgeable in the
structure and use of the equipment.

Certification of Crane Operators (CCO)


The National Commission for the Certification of Crane Operators (CCO) is an independent not-for-profit
corporation formed to establish and administer a nationwide program of certification of operators. This
organization establishes set standards for measuring the knowledge and proficiency for the safe operation
of crane equipment.

Functional
A safety device shall be in use and operating while the crane is in use. Functional does not mean merely
“capable of performing” for purposes of these safety requirements.

Jib
An extension attached to the boom point to provide added boom length for lifting specified loads.

On-Rubber Pick and Carry


A lift made in conjunction with the manufacturer’s load chart without the use of outriggers in which the
load is lifted and moved under the power of the crane unit.

Rolling Outriggers
An accessory component that is attached to the outrigger assembly in lieu of outrigger pads which allow
for pick and carry with the outriggers extended. Use of this equipment requires that the component and
load chart is approved by the manufacturer or certified agent.

Qualified Person
A person who, by possession of a recognized degree or certificate of professional standing, or who, by
extensive knowledge, training, and experience, has successfully demonstrated the ability to solve
problems relating to the subject matter and work.

PROCEDURES

Bid Procedures
1. Each subcontractor shall submit in its bid set, a declaration that all crane equipment utilized on
Snyder Langston projects will meet the criteria required in the bid specifications for safe crane
operation.
2. Each subcontractor will receive the Crane Safety Manual: Policies and Procedures, Crane Operation
Survey, and a Pre-Erection Hazard Analysis form upon award of contract.
3. The subcontractor shall provide copies of the Crane Safety Manual with Policies and Procedures,
Crane Operation Survey, and a Pre-Erection Hazard Analysis form for each crane rental company
who plans to provide crane equipment for use on Snyder Langston projects prior to a pre-job
conference.

Subcontractor Safety Start-up Meeting


Each subcontractor, along with a representative of the crane provider, shall attend a pre-job start-up
meeting with Pre-Erection Hazard Analysis form completed.

Page 6
Revised: August 5, 1999

Crane Survey Procedure


1. The subcontractor shall notify the Snyder Langston Project Superintendent at least 72 hours in
advance of a scheduled crane arrival. The notification shall include the following information:
1.1. On-site subcontractor contact name
1.2. Crane type (Hydraulic, conventional, crawler, etc.)
1.3. Crane capacity
1.4. Arrival time for crane assembly
1.5. Work start time
1.6. Crane owner / rental company name
1.7. Type of work to be performed (tilt-up panels, steel erection, set air-conditioning unit,
etc.)
1.8. Copy of pre-authorized critical lift plan as needed
2. The Snyder Langston Project Superintendent shall schedule the crane surveyor within 48 hours for
arrival at the job site concurrent with the arrival time of the crane equipment for viewing of the
assembly crane equipment.
3. Upon approval by Snyder Langston’s Project Superintendent, the equipment survey portion of this
procedure may be conducted at the crane owner’s location 24 hours prior to the crane equipment’s
arrival at the job site.
4. Each survey shall commence at “build up” of the crane. Crane owners should plan for ½ hour of
additional “build up” time for the survey.
5. Upon arrival at the job site, the crane surveyor shall report directly to the Snyder Langston office,
then proceed to the location of the crane assembly area.
6. The crane surveyor shall introduce himself or herself to the subcontractor and crane crew giving a
brief explanation of the survey procedure.
7. Where a deficiency requires repairs, replacement of equipment, or additional testing which may result
in down time and additional expenses, the crane owner shall be afforded the opportunity to determine
the method of correction which is acceptable to Snyder Langston, the crane surveyor, and the
subcontractor.
8. The crane survey shall include the inspection of the crane, accessory equipment to be used on the
project, and below-the-hook lifting devices that will be used for lifts on the project.
9. The surveyor shall record all information required on the Crane Operation Safety Survey form and
identify any safety deficiencies noted as follows:
9.1. Note deficiency on report along with plan of action for correction (crane crew corrected,
crane company replacing component, etc.)
9.2. Report deficiency to the crane operator or oiler for initial correction.
9.3. Where a deficiency can not be corrected prior to scheduled work time, a verbal and
written report shall be provided to the Snyder Langston Project Superintendent which
includes the following information:
9.3.1.1. Persons notified of deficiency (operator, oiler, subcontractor, etc.)
9.3.1.2. Severity of deficiency.
9.3.1.3. Recommended plan of action.
10. The crane surveyor shall view the set up of the crane and operation of the crane in order to evaluate
the safe operation and use of the crane equipment.
11. Upon surveying the assembly, set up, and operation of the crane equipment, the survey report, along
with all deficiencies noted and recommended plans of action shall be provided to the Snyder
Langston Project Superintendent.

Page 7
Revised: August 5, 1999

12. Under most circumstances, the survey is completed on site between 1 and 3 hours.
12.1. If on site time is expected to exceed 4 hours, the surveyor should notify the Project
Superintendent.
12.2. If on site time is expected to exceed 8 hours, the surveyor should notify the
Snyder Langston Safety Manager.
Note: Failure to notify the persons specified above shall result in the reduction or
nonpayment of the surveyor’s charges that exceed the said time periods.

CRANE SAFETY REQUIREMENTS


1. Report any unsafe conditions to the subcontractor foreman or Project Superintendent immediately.
2. Access for entry and assembly of the crane shall be free from obstructions, underground hazards, and
overhead power lines.
3. All crane equipment and operation of crane equipment shall meet the requirements of the
manufacturer, ANSI, ASME, and OSHA.
4. Crane equipment shall have the required inspection and proofload testing certificates current and
available upon arrival at the job site.
5. Lifting beams (commonly known as “spreader bars”) shall conform to ANSI B30.20, 1985
regulations which requires the following permanent markings:
5.1. Manufacturer’s name
5.2. Serial number (ID #)
5.3. Weight of the bar if over 100 lbs.
5.4. Rated load
5.5. Initial Proofload testing at 125% of the lifting beam’s capacity.
6. Proof of initial load testing shall be provided for all lifting beams. Load test shall not exceed 125% of
the rated load.
7. Engineering data shall be provided to Snyder Langston Management on all specialized below-the-
hook lifting devices.
8. No crane shall be operated near high voltage as follows:
Π0 to 50 kV 10 feet
Πover 50 to 200 kV 15 feet
Πover 200 to 350 kV 20 feet
Πover 350 to 500 kV 25 feet
Πover 500 to 750 kV 35 feet
Πover 750 to 1000 kV 45 feet
9. Crane shall travel with no load and the boom or mast lowered near high voltage as follows:
Πover 0 to 50 kV 6 feet
Πover 50 to 345 kV 10 feet
Πover 345 to 750 kV 16 feet
Πover 750 to 1000 kV 20 feet
10. No loads shall be lifted over personnel.
11. No one shall place their hands or any other portion of the body under a load suspended by the crane.
12. No unauthorized personnel shall be working within the lifting area3 of the crane.
13. Yellow caution tape shall be used to prevent personnel from entering the crane rotation area.
14. All personnel shall be clear of crawler tracks while the crane is moving.
15. All personnel except for the operator and oiler shall be clear of the crane rotating area during its
operation.
16. A designated signal person shall provide direction to the operator using the standard hand signals or
radio communications that are common to the industry.

3
The lifting area encompasses that area where the boom is likely to swing over during the lift. This area should be
clear of any person who is not directly involved with the lifts being performed.
Page 8
Revised: August 5, 1999

17. Operation of crane equipment by persons designated as the oiler shall be conducted under the direct
supervision of an experienced operator during non-critical lifts. Where such lifts are conducted,
notice shall be given to all employees working with the crane equipment.
Note: Direct supervision requires the experienced operator to be present at the
operator’s station during all lifts.
18. No lifts shall exceed 75% of the manufacturer’s load rating unless a written critical lift plan has been
submitted and pre approved. Where tilt-panels panels are being lifted, no lifts shall exceed 85% of
the manufacturer’s load rating unless a written critical lift plan has been submitted and pre approved.
19. The manufacturer’s load chart shall be affixed to the crane or located in the operator’s cab accessible
to the operator.
20. All lifts and crane configurations shall be consistent with the manufacturer’s requirements and load
charts.
21. When pick and carry operations occur, the ground shall be smooth, level, and compacted, free from
obstructions, underground hazards, and overhead power lines.
22. No cribbing shall be placed under the crane axle, frame, or out rigger extension beams.
23. Jib and boom shall be free from structural damage that exceeds the manufacturer’s maximum
allowable tolerances.
24. Anti two-blocking device shall be functional and operational on all cranes equipped with such device.
(All cranes that are operated in states where anti-two blocking devices are required shall be equipped in accordance with
that state’s standards)
25. A load indicator shall be on all load lines in use on mobile cranes that exceed 50 tons rated capacity
or 200 feet of boom.
26. An electronic boom angle indicator shall be provided on all hydraulic cranes exceeding 15 tons rated
capacity or a 60 feet boom length.
27. No crane shall be operated in wind speeds that exceed 35 mph or the manufacturer’s
recommendations which ever is the lesser wind speed.
27.1. Where surface area of material being lifted creates a sail affect, the crane
may be required to cease operating at lower wind speeds than stated.
28. Wind speed indicators shall be provided by Snyder Langston at each site location and affixed to a
pole or structure at the highest point possible above the ground level.
28.1. Where possible, the wind indicator shall be properly affixed to the crane
boom.
29. No person shall disable or circumvent a safety device while the crane is performing lifting service.

INSPECTION OF CRANE EQUIPMENT

California Projects
All cranes assembled or operated on Snyder Langston Projects located in California shall have a current
annual certificate of inspection and a current quadrennial certificate of inspection and proofload test
issued by a crane surveyor licensed and accredited by the California Division of Occupational Safety and
Health Administration (Cal-OSHA). Copies of these certifications shall be located on the crane upon its
arrival at the job site and provided for inspection by a qualified Snyder Langston representative prior to
operation of the crane on any project. If either certificate expires while in operation on a project, the
crane shall cease its operation until such time the crane is inspected, tested, and a current certificate has
been issued by a licensed crane surveyor.

Other States
No crane shall be operated or assembled prior to providing proof of an annual safety inspection performed
by a qualified person. The inspection criteria and document shall be consistent with Federal Occupational
Safety and Health Administration, Department of Labor regulations and regulatory agency of the
governing state that the project is located. Proof of such inspection shall be located on the crane upon its
arrival at the job site and provided for inspection by a qualified Snyder Langston representative prior to
operation of the crane on any project.

Page 9
Revised: August 5, 1999

LOAD TESTING OF JIBS AND ROLLING OUTRIGGERS


This section applies to all California projects and other
states that require proofload testing of crane equipment
All cranes that perform lifts with the jib attachment or rolling outriggers on Snyder Langston projects
shall have a current certification4 stating that the jib and rolling outriggers have been proofload tested by a
qualified person. Proof load tests shall be performed during the initial proofload testing and every four
years thereafter, unless a structural repair has been performed on the crane. If a structural repair has been
performed (even if the jib was not damaged) a load test shall be performed prior to placing the crane back
into service. No proof load test of the jib or rolling outriggers is required during the annual certification
as long as proof load testing of these components has been performed in accordance with the
requirements specified above. Where the crane owner elects not to test the jib or rolling outriggers, it
shall be noted on the certificate and the jib or rolling outriggers shall not be used until load testing has
been successfully completed. These requirements apply equally to telescopic and lattice boom cranes.

ANTI TWO-BLOCK DEVICES


This section is a minimum requirement for projects in all states.
Cranes manufactured after February 28, 1992
Telescopic boom cranes operated on Snyder Langston projects shall be equipped with a functional anti
two-block damage prevention feature. Lattice boom cranes operated on Snyder Langston projects shall
be equipped with a functional anti two-block damage warning feature.

Cranes manufactured before February 28, 1992


All cranes equipped with an anti two-blocking device shall be operated with the device fully functional
during all lifts conducted on Snyder Langston projects.

LOAD RATING CHARTS


This section is a minimum requirement for projects in all states.
A durable load chart with clearly legible letters and figures provided by the crane manufacturer or a
certified agent experienced and familiar with the characteristics of the crane equipment shall be securely
fixed (where the manufacturer’s load chart is provided in a binder or other book form, the chart shall be
located in the operator’s cab) to the crane in a location clearly visible to the operator or within reach of
the operator while at the control station. The chart shall contain a full and complete range of crane load
ratings, consistent with the manufacturer’s' recommendations, at all stated operating radii or boom angles
and for all permissible boom lengths, jib lengths and angles, also alternate ratings for use and non-use of
optional equipment on the mobile crane, such as outriggers and counterweights which affect ratings. The
chart shall also contain essential precautionary or warning notes relative to limitations on equipment and
operating procedures, including indication of the least stable position. In addition, no crane shall be
rerated unless such rating changes are approved by the certified agent. Load ratings shall be expressed in
terms related to method of measuring boom angle and length or lifting radius.

4
Cal-O.S.H.A. Title 8, plate V or equivalent proof for cranes located in states outside of California. See attachment
1 for example.
Page 10
Revised: August 5, 1999

Interpretation
Where the actual boom angle does not match the values shown on the load chart, the value used must be
the next lower boom angle number. Where the actual load radius does not match the values shown on the
load chart, the value used must be the next higher radius number.

Example
The load is to be placed at a 55-ft radius at 47° boom angle. The load chart values are shown for 50-ft.
radius at 55° boom angle with the next value at 60-ft. radius at 45° boom angle. The capacity reflected at
the 60-ft. radius at 45° boom angle must be used for this example since no capacity values are given for
the actual load radius and boom angle.

CRITICAL LIFTS
A critical lifts is established where any one of the following conditions are created:
1. Where in the crane’s current configuration at any point during the lift, a gross
load weight exceeds 75% of the capacity of the crane, or 85% of the capacity
of the crane where tilt-up panels are erected.
2. A single lift that two or more cranes are used including tandem lifts and
tailing cranes.
3. Lifts made in close proximity of power lines as defined by the voltage
clearance specifications described above.
4. Lifts involving specialized or unique and complex rigging equipment.
5. Hoisting of suspended work platforms.
6. Static tower crane erection and dismantelment.
7. Making lifts below the ground level where the crane is positioned.
Note: Where the below the ground lift is minimal, a critical lift plan may not
be required.

Critical Lift Plan


Where a critical lift will be performed, a written critical lift plan shall be submitted to Snyder Langston
prior to commencing with the lift. The written plan shall include the following:
1. Crane manufacturer, capacity, and all specifications for the configuration to
be used for the lift.
2. Load chart data for the crane to be used to make the lift.
3. Total calculated weight of the load to be lifted including all rigging and other
deductions consistent with the manufacturer’s load chart.
4. Diagrams of the lift that provides geometrical conditions of the load, rigging,
and all crane positions during the lift. The drawing shall provide the
following:
A. Locations of all components to be lifted prior, during and after
the lift is completed.
B. Radius points.
C. Swing patterns.
D. In the event that the lift must be aborted, positions where the
load may be safely landed.
E. Areas where any personnel, public, and vehicles must be
evacuated during the lift.
5. Potential ground loading for each point of contact by the crane in selected
locations in which the crane will perform the critical lift.

Page 11
Revised: August 5, 1999

6. Soil and subsurface data and information pertaining to the location on which
the crane used for the critical lift will be positioned. This information shall
be procured from an authoritative source such as a geotechnical engineer or a
professional civil engineer registered in the state where the project is located.
This information may be available from Snyder Langston for selected
locations on some projects.
7. An engineer shall use the data provided in #5 and #6 above to verify and
confirm the following:
A. That the soil and subsurface conditions are capable of
supporting all loads imposed during the critical lift.
B. That the designs of cribbing and other supports used under the
crane load points are appropriate to safely transfer such loads.
8. Signature and stamp on the plan by a registered professional engineer
licensed in the state in which the project is located, evidencing review of the
plan as meeting the requirements set forth in this manual and that all loads
and load information and calculations contained in the plan are approved,
acceptable and safe to perform.
9. Operator qualifications.
10. Method by which communication will be provided to the crane operator.
(Designated signal person, two-way radio, hard wire phone system, etc.)
11. A critical lift hazard analysis which identifies the particular hazards
associated with the lift and the means and methods to reduce, mitigate, or
eliminate the hazards.
12. Emergency action plan.
The written plan shall be submitted 72 hours prior to any critical lift for review by Snyder Langston’s job
superintendent and crane surveyor. No critical lifts shall be conducted prior to such approval.

CRANE SUSPENDED WORK PLATFORMS


The use of a crane or derrick to hoist employees on a personnel platform is prohibited, except when the
erection, use, and dismantling of conventional means of reaching the worksite, such as a personnel hoist,
ladder, stairway, aerial lift, elevating work platform or scaffold, would be more hazardous or is not
possible because of structural design or worksite conditions. If a crane suspended work platform is used,
its use shall be conducted in accordance California Code of Regulations, Title 8, § 5002. Where work is
conducted outside of California, Federal O.S.H.A., 29 C.F.R. 1926 § 550(g) shall be followed unless the
regulations of the state where the project is located exceed these requirements.

QUALIFICATIONS OF CRANE OPERATORS AND SURVEYORS


All persons who perform crane safety surveys or operate crane equipment on Snyder Langston projects
shall be adequately trained and experienced on the type of crane and lifts that are to be performed.
Effective June 1, 2000, Snyder Langston requires all crane operators to be certified under the CCO or an
equivalent program that has been reviewed by an independent assessment service (e.g. Buros Institute)
accepted by the Snyder Langston’s Safety Manager. Proof of CCO certification or its equivalent (as
defined under Crane Operator) shall be provided to Snyder Langston’s qualified crane surveyor or Project
Superintendent prior to commencing any crane operations. It shall be the responsibility of the
subcontractor to ensure that all operators hired or contracted with are qualified, trained, and experienced
prior to commencing with lifts on Snyder Langston projects. In addition, all crane surveyors shall be
required to complete CCO testing.

Page 12
Revised: August 5, 1999

INTENT
The intent of this Mobile Crane Safety Policy and Procedure Manual is to provide guidance and clarity to
existing regulations and requirements for the safe operation of crane equipment. The requirements set
forth above shall be followed by all subcontractors who own or hire crane equipment to work on Snyder
Langston projects.

Printed name Signed

Title Company

Date

Page 13
Revised: August 5, 1999

Subcontractor notifies Project


Superintendent 72 hours prior to crane
arrival and provides copies of
critical lift plans upon arrival Crane Safety
Project Superintendent schedules crane
Survey
surveyor 48 hours prior to crane arrival
Process
Crane company
Subcontractor faxes Project issues insurance
Superintendent the Pre-Erection Hazard documents to Snyder
Analysis 24 hours prior to crane arrival Langston 24 hours
Insurance and prior to crane arrival
Evaluation
Requirements
Met
Project Superintendent provides crane
surveyor with pre-job evaluation and
critical lift plans upon arrival Yes No

Delay Crane
Arrival

Crane Surveyor
evaluates crane
documentation, Unsafe
equipment, assembly, Condition
set-up, accessories, Exists
lifting devices, and
operation

Plan of action with


Notify GC
crane operator
Superintendent
No
& Safety
discrepancies Plan of action with
found Management
subcontractor

Plan of action
Crane Surveyor Unsafe reported to
evaluates crane Condition Snyder Langston
operation Exists Project
Superintendent

Unsafe
condition
Safe to corrected
conduct lifts and/or
lift plan
revised

Survey report provided to


Project Superintendent
and Safety Office

Page 14
Revised: August 5, 1999

Crane Safety Survey


Procedure
SURVEYOR WILL
Review Erection Hazard Analysis
Form with Project Superintendent,
Subcontractor and Crane Crew

Review lift plans


with Project Superintendent,
Subcontractor and Crane Crew

Record crane data


and
Operator/Oiler background

Survey boom and accessories gear prior


to assembly of crane

Evaluate the crane and all critical


components

Evaluate the below-the-hook


lifting devices

Evaluate the set up of the crane and area


that the lifts will be performed

Evaluate the weight of lifts


and load chart criteria

Evaluate the operation of the crane during


setup and while performing lifts

Survey report provided to


Project Superintendent
that includes completed
forms with any restrictions
or plans of action
Page 15
Revised: August 5, 1999

PRE-ERECTION HAZARD ANALYSIS FOR GENERAL CONTRACTOR


ÍRequired 72 Hours Prior to Crane ArrivalÌ
Subcontractor Contact:
Project Name: Phone:
Project Location: Job No.:
Date:
I have read and understand the Snyder Langston crane
safety policies and procedures. Yes ❏ No ❏
Crane Equipment
Type of work Tilt – up panel ❏ Steel erection ❏ Other__________________________
Crane capacity: _____________________ Boom length: ____________________________________
Maximum pick radius on Maximum pick weight
this project _____________________ on this project ____________________________________
Crane Type: Telescoping Boom ❏ Lattice Boom ❏ Rough Terrain ❏
Truck mounted ❏ Crawler Mounted ❏ Other:________________________
Accessory gear: Rolling outriggers ❏ Jib ❏ Other:________________________

Lift Analysis
Will any lifts exceed 75% of the crane’s rated capacity? Yes ❏ No ❏ N/A ❏
If yes, have you submitted a written critical lift plan? Yes ❏ No ❏ N/A ❏
Will any lifts require on rubber pick and carry operation? Yes ❏ No ❏ N/A ❏

Pre-Erection Hazard Analysis


A. Access for cranes, trucks, and other erection Equipment:
1. Haul road for cranes and trucks OK ❏ N/A ❏ See ❏
Notes
2. Adequate entrance into and out of project OK ❏ N/A ❏ See ❏
Notes
3. Use of public access requiring traffic control or permits OK ❏ N/A ❏ See ❏
Notes
4. Adequate area for crane assembly OK ❏ N/A ❏ See ❏
Notes
5. Adequate area for crane disassembly OK ❏ N/A ❏ See ❏
Notes
6. Existing structures on site OK ❏ N/A ❏ See ❏
Notes
7. Truck staging area available OK ❏ N/A ❏ See ❏
Notes
8. Access outside of structure OK ❏ N/A ❏ See ❏
Notes
B. Ground Conditions
1. Level OK ❏ N/A ❏ See ❏
Notes
2. Compaction to support crane loads OK ❏ N/A ❏ See ❏
Notes
3. Ramps - - gradability OK ❏ N/A ❏ See ❏
Notes
4. Crane restrictions (excavations, shoring, OK ❏ N/A ❏ See ❏
underground structures) Notes
5. Slab thickness will support crane OK ❏ N/A ❏ See ❏
Notes
C. Utilities
1. Overhead wires (provide method used to maintain clearance in notes OK ❏ N/A ❏ See ❏
section) Notes
2. Underground vaults, sewer, gas, fiber optics, etc. OK ❏ N/A ❏ See ❏
Notes
3. Airport clearance OK ❏ N/A ❏ See ❏
Notes
4. Airport flag or light OK ❏ N/A ❏ See ❏
Notes
D. Other condition not addressed above: OK ❏ N/A ❏ See ❏
__________________________________ Notes

Information provided by:


Print Signature

Page 16
Revised: August 5, 1999

Date Page One of ____

PRE-ERECTION HAZARD ANALYSIS NOTES

Subcontractor Subcontractor
Name Contact:
Job Name: Subcontractor
Phone:
Job Location: Job No.:

Item No. Description and Plan of action


C-1 (Example) Crane must be operated near high voltage power
lines for the erection of east corner of building

Plan of Crane company has installed a swing warning device that will
action sound an alarm before the crane has swung into
the restricted zone of the power lines. The alarm increases
its sound as the crane nears the zone.

Subcontractor Name

Subcontractor Subcontractor

Contact Name Contact’s signature


Print

Page 17
Revised: August 5, 1999

Date Page One of ____


Continued from Page One…
Item No. Description and Plan of action

Subcontractor’s Initials: ___


Surveyor’s Initials: ___

Surveyor’s Name Surveyor’s Signature


Page 18
Revised: August 5, 1999

Surveyor Assignment No.:________


Date of survey:________
Survey Form No. ________

CRANE OPERATION SAFETY SURVEY


Attention: SURVEY IS BASED ON THE CONDITION OF CRANE AT THE TIME OF SURVEY.
CORRECTIONS AND CHANGES MADE AS A RESULT OF THIS SURVEY SHALL BE WRITTEN ON THE
SURVEY NOTES FORM.

Subcontractor Subcontractor
__________________________ Contact Name: _____________________________________

Project Name: Subcontractor


__________________________ Phone Number: _____________________________________

Project Location: Crane Owner


__________________________
Name: _____________________________________
SL’s Job Number: Crane Owner
__________________________ Phone Number: _____________________________________

Superintendent: On Site Survey


__________________________ Time: Begin: _________ End: __________

Crane Identification
Crane Configuration at Time of Survey:
Crane Configuration Upon Surveyor’s Arrival:
Crane Assembled: ❏ Crane Disassembled: ❏
Manufacturer: Unit Number:
___________________________________________ _______________________
Model Serial Number:
Number:
___________________________________________ _______________________
Boom Length: Jib Length: Crane
Capacity:
_____________________________ ______________ ____________
Boom Section Base Tip Mid Insert 1 Insert 2 Insert 3 Insert 4 Insert 5 Insert 6 Jib Jib
Identification
_____ _____ ____ ______ ______ ______ ______ ______ ______ ___ ___
Numbers:
Crane Type: Telescoping Boom ❏ Lattice Boom ❏ Rough Terrain ❏
Truck Mounted ❏ Crawler ❏ Mobile Tower ❏
Mounted
Accessory Rolling Outriggers ❏ Jib ❏ Jib
gear: Configuration:___________________
Counter
Weight
Jib Length: __________________
Configuration: _____________________________

White-Snyder Langston Safety Manger Canary-Snyder Langston Project Superintendent Blue-Surveyor Green-Invoice

Page 19
Revised: August 5, 1999

Surveyor Assignment No.:________


Date of survey:________
Survey Form No. ________

Crane Evaluation
1.0 Documentation
1.1 Annual certification (attach copy) YES ❏ See Notes ❏
1.2 Quadrennial certification (attach copy) YES ❏ N/A ❏ See Notes ❏
1.3 Manufacture’s load chart accessible on the crane to the operator YES ❏ See Notes ❏
1.4 Operator’s manual on the crane YES ❏ See Notes ❏
1.5 Pre-Erection Hazard Analysis completed (attach copy) YES ❏ See Notes ❏
1.6 Other: ___________________________________________________ YES ❏ N/A ❏ See Notes ❏
2.0 Safety Devices
2.1 Load moment indicator is functioning and accurate YES ❏ N/A ❏ See Notes ❏
2.2 Anti two-block device is functioning and operational YES ❏ See Notes ❏
2.3 Boom angle indicator is functioning and accurate YES ❏ See Notes ❏
2.4 Other: ___________________________________________________ YES ❏ N/A ❏ See Notes ❏
3.0 Structural Integrity
3.1 Boom sections OK ❏ See Notes ❏
3.2 Jib assembly OK ❏ N/A ❏ See Notes ❏
3.3 Outrigger supports OK ❏ N/A ❏ See Notes ❏
3.4 Main frame OK ❏ See Notes ❏
3.5 Other: ___________________________________________________ OK ❏ N/A ❏ See Notes ❏
4.0 General Components
4.1 Main load line OK ❏ N/A ❏ See Notes ❏
4.2 Auxiliary load line OK ❏ N/A ❏ See Notes ❏
4.3 Boom hoist line OK ❏ N/A ❏ See Notes ❏
4.4 Outriggers extend and deploy OK ❏ N/A ❏ See Notes ❏
4.5 Manufacturer’s counter weights installed in accordance with the OK ❏ See Notes ❏
load chart
4.6 Sheaves and drums checked for excessive wear and damage OK ❏ See Notes ❏
4.7 Tire condition for on rubber picks OK ❏ N/A ❏ See Notes ❏
4.8 Other: ___________________________________________________ OK ❏ N/A ❏ See Notes ❏

Page 20
Revised: August 5, 1999

Surveyor Assignment No.:________


Date of survey:________
Survey Form No. ________

Operator and Oiler History


5.0 Operator
Name: Emergency contact person: _________________________________

__________________________________________ Emergency phone number: _________________________________

5.1 How many years experience operating on this type of crane?


______Years
5.2 How many years of experience with the type of lifts on this Job?
(tilt-up panel work, steel erection, etc) ______Years

5.3 Has the operator received a copy of General Contractor’s crane safety YES ❏ See Notes ❏
policy and procedures?
5.4 Does the operator use and understand the load-rating chart on this YES ❏ See Notes ❏
crane?
5.5 Has the operator been instructed that he should not continue with YES ❏ See Notes ❏
any lift that creates an unsafe condition?
5.6 Does the operator have the Certified Crane Operator’s (C.C.O.) YES ❏ See Notes ❏
certificate?

5.6.1 C.C.O. Number: ________________________ Issued: ____ Expires: ______

5.7 Does the operator have any other crane operator’s certificates? YES ❏ N/A ❏ See Notes ❏
Issue
5.8 Number of certificates: Issued
___ By: ___________ Date: ______ Expires: __________

6.0 Oiler
Name: Emergency contact person: _________________________________

_____________________________________ Emergency phone number: _________________________________

6.1 How many years experience oiling on this type of crane?


______Years
6.2 How many years of experience with the type of lifts on this Job?
(tilt-up panel work, steel erection, etc) ______Years

6.3 Has the oiler received a copy of General Contractor’s crane safety policy YES ❏ See Notes ❏
and procedures?
6.4 Does the operator use and understand the load-rating chart on this crane? YES ❏ See Notes ❏
6.5 Has the oiler been informed that he should notify the operator of any YES ❏ See Notes ❏
unsafe condition?
6.6 Has this Oiler been informed of the General Contractor provision YES ❏ See Notes ❏
restricting operation of crane equipment to qualified operators only?

Page 21
Revised: August 5, 1999

Surveyor Assignment No.:________


Date of survey:________
Survey Form No. ________

Below-the-Hook Lifting Devices


7.0 Lifting Beams (ANSI B30.20)
7.1 Manufacture’s name permanently marked on bar YES ❏ N/A ❏ See Notes ❏
7.2 Serial Number (ID #) permanently marked on bar YES ❏ N/A ❏ See Notes ❏
7.3 Weight of bar (if over 100 lbs.) permanently marked on bar YES ❏ N/A ❏ See Notes ❏
7.4 Rated load capacity permanently marked on bar YES ❏ N/A ❏ See Notes ❏
7.5 Proof of rated load test not exceeding 125% capacity of the bar YES ❏ N/A ❏ See Notes ❏
7.6 Other: __________________________________________________ YES ❏ N/A ❏ See Notes ❏
Set Up and Operation
8.0 Lift Information
The following lift information provided by: Name: _________________ Company ____________________
8.1 What is the heaviest lift to be lifted with this crane? Weight _______Lbs.
At what radius? Radius _______Ft.

8.2 What is the maximum radius this crane will be lifting? Radius _______Ft.
Weight of lift? Weight _______Lbs.

8.3 What is the maximum load for pick and carry lifts Weight _______Lbs.
Maximum radius for pick and carry lifts? Radius _______Ft.

8.4 Does this crane have an approved load chart for on rubber picks? YES ❏ N/A ❏ See Notes ❏
8.5 Does this crane have an approved load chart for rolling out YES ❏ N/A ❏ See Notes ❏
riggers?
8.6 All lifting procedures conform with the load chart requirements YES ❏ See Notes ❏
8.7 All lifts will be performed without exceeding 80% of the rated YES ❏ See Notes ❏
capacity
8.8 Written plans provided to General Contractor Safety Management YES ❏ N/A ❏ See Notes ❏
for critical lifts

8.9 The Critical lift plan has been provided by: Company: ______________________________
Name: ______________________________
Title: ______________________________
Date ______________________________

8.10 Wind speed limitation specified by the manufacturer ____ M.P.H See Notes ❏
8.11 Other: __________________________________________________ YES ❏ N/A ❏ See Notes ❏

Page 22
Revised: August 5, 1999

Surveyor Assignment No.:________


Date of survey:________
Survey Form No. ________

9.0 Set up
9.1 Crane is level YES ❏ See Notes ❏
9.2 Ground compacted and stable YES ❏ See Notes ❏
9.3 Properly cribbed under outrigger pads only YES ❏ N/A ❏ See Notes ❏
9.4 Crane configuration is compatible with manufacture’s YES ❏ See Notes ❏
requirements
9.5 Area of travel is level, clear, and stable for pick and carry YES ❏ See Notes ❏
9.6 Area has be checked for underground utilities in crane area YES ❏ See Notes ❏
9.7 Outriggers are fully extended deployed with the tires off the YES ❏ N/A ❏ See Notes ❏
ground or used in compliance with manufacturer’s specifications
9.8 Airport Flag is properly attached to boom Tip YES ❏ N/A ❏ See Notes ❏
9.9 Other:___________________________________________________ YES ❏ N/A ❏ See Notes ❏
10.0 Operation
10.1 Pre lift meeting held with crane and rigging crew YES ❏ See Notes ❏
10.2 Designated signal man YES ❏ N/A ❏ See Notes ❏
10.3 Operation of crane conducted in a smooth and safe manner YES ❏ See Notes ❏
10.4 Lifting sequence and plan is known and followed by the operator YES ❏ See Notes ❏
10.5 The crane is operated the required distance from overhead power YES ❏ N/A ❏ See Notes ❏
lines
10.6 Tag lines are used on loads YES ❏ N/A ❏ See Notes ❏
10.7 Other:__________________________________________________ YES ❏ N/A ❏ See Notes ❏

Assessment
11.0 Results
11.4 This crane may proceed with lifts as scheduled YES ❏ See Notes ❏
11.5 This operator may proceed with lifts as scheduled YES ❏ See Notes ❏
11.6 The accessory gear may be used as scheduled YES ❏ N/A ❏ See Notes ❏
11.7 The below-the-hook lifting devices may be used as scheduled YES ❏ N/A ❏ See Notes ❏
11.9 Other:__________________________________________________ YES ❏ N/A ❏ See Notes ❏
Subcontractor’s Name Surveyor’s Name
Print Print

Subcontractor’s signature Surveyor’s Signature

Page 23
Revised: August 5, 1999

Date
Page One of ___
CRANE OPERATION SURVEY NOTES

THESE NOTES APPLY TO ITEMS IDENTIFIED ON


CRANE OPERATIONS SAFETY SURVEY FORM NUMBER:

Job Job No.:


Name: ______________________________ _________________________________
Crane Manufacturer:
Owner: ______________________________ _________________________________
Model Serial Number: Unit
Number: ______________________________ ___________ Number: ________

Item No. Description and Plan of action


1.1 (Example) No annual certification on the crane
Plan Crane owner will fax copy to Snyder Langston job
of office prior to crane going to work.
action
:

Subcontractor Name

Subcontractor Subcontractor
Contact Name Contact’s signature
Print

Surveyor’s Name Surveyor’s Signature


Page 24
Revised: August 5, 1999

Page ____ of ____


Survey Form Number:___________
Continued from Page One…
Item No. Description and Plan of action

Subcontractor’s Initials: ___


Surveyor’s Initials: ___

Page 25
Revised: August 5, 1999

MOBILE CRANE SAFETY BID SPECIFICATIONS


1.1 RELATED DOCUMENTS
A. Crane Manufacture’s recommendations and requirements.
B. American Society of Mechanical Engineers/American National Standards Institute
(ASME/ANSI) B30 codes.
C. Department of Labor, Occupational Safety and Health Administration (Fed-OSHA) 29 CFR
Parts 1910 and 1926.
D. California, Occupational Safety and Health Administration (Cal-OSHA) Title 8, Group 13
regulations OR applicable state regulations for job site location.
E. Snyder Langston Mobile Crane Safety Manual
F. Snyder Langston Pre-Erection Hazard Analysis forms
G. Snyder Langston Crane Operation Safety Survey forms
1. Documents identified in E, F, and G above are available upon request.
2.1 SUMMARY
A. These safety specifications shall apply to all mobile cranes exceeding 3 tons rated
capacity utilized for lifting of materials or personnel on all Snyder Langston projects.
B. Cranes with a rated capacity of 14.5 tons or more shall under go the Safety surveys
identified in section 6.1 of these specifications.
3.1 RESPONSIBILITIES
A. The Snyder Langston Project Superintendent has complete authority to cease any crane
activity or operation on the project.
B. The subcontractor shall ensure that mobile crane lifting operations are performed within
the guidelines set forth by the governing authorities and Snyder Langston at all times.
Any delays or down time due to the determination or correction of any crane safety
deficiency shall be at the subcontractor’s own expense.
C. The surveyor shall inform Snyder Langston’s Safety Manager, Snyder Langston’s Job
Superintendent, and the crane owner respectively if discrepancies are identified during the
survey process that may affect the safe operation of the crane and propose a plan of
action to assist in the elimination of the deficiency.
D. The crane owner shall provide all required documentation such as manufacturers load
charts, manufacturer’s maintenance criteria, and proof of safety certifications consistent
with the state and federal requirements for inspection by the crane surveyor, Snyder
Langston, the project superintendent, and the subcontractor. The crane owner shall
provide Snyder Langston’s management with a “certificate of insurance” and acceptable
endorsement naming Snyder Langston & the project owner & the subcontractor as
additional insured on its general liability coverage 24 hours prior to the arrival of any
crane equipment to the job site. Any delays due to operations or equipment that are
adverse to the safety requirements set forth in the Snyder Langston Mobile Crane Safety
Manual shall be at the crane owner’s and/or subcontractor’s own expense.
E. Any crane operator, who determines that a lift is unsafe to be performed, shall refuse to
continue operation of the crane. The crane operator shall work directly with the crane
surveyor and provide the surveyor with the information required on all Snyder Langston
crane survey forms.
F. No crane oiler shall operate any crane equipment unless he possesses the qualifications
of a bona fide crane operator. This limitation does not include positioning of the crane
during relocation, assembly, or disassembly.
4.1 QUALIFICATIONS OF CRANE PERSONNEL
A. Effective June 1, 2000, all crane operators and crane surveyors shall be certified under
the National Commission for the Certification of Crane Operators (C.C.O.) or an equivalent
program that has been reviewed by an independent assessment service (e.g. Buros
Institute) accepted by the Snyder Langston management.

Page 26
Revised: August 5, 1999

5.1 CRANE OPERATION SAFETY REQUIREMENTS


A. All crane equipment and operation of crane equipment shall meet the requirements of the
manufacturer, ANSI, ASME, and OSHA.
B. Lifting beams (commonly known as “spreader bars”) shall conform to ANSI B30.20, 1985
regulations and include the following permanent markings:
1. Manufacturer’s name.
2. Serial number (ID #).
3. Weight of the bar if over 100 lbs.
4. Rated Load.
5. Initial Proofload testing at 125% of the lifting beam’s capacity.
C. Cranes shall maintain the minimum clearance from power lines as specified in the Snyder
Langston Mobile Crane Safety Manual.
D. No lifts shall exceed 75% of the manufacturer’s load rating unless a written critical lift
plan has been submitted and pre approved. Where tilt-panels panels are being lifted, no
lifts shall exceed 85% of the manufacturer’s load rating unless a written critical lift plan
has been submitted and pre approved.
E. No crane shall be operated in wind speeds that exceed 35 mph or the manufacturer’s
recommendations which ever is the lesser wind speed.
1. Where possible, wind speed indicators shall be attached to the crane boom.
2. Snyder Langston will provide a wind indicator at each site location.
F. No person shall disable or circumvent a crane safety device while the crane is performing
lifting service.
6.1 CRANE SAFETY DEVICES
A. An Anti two-blocking device shall be functional and operational on all cranes
manufactured after 1991.
B. A load moment indicator shall be on all load lines in use on mobile cranes that exceed
50 tons rated capacity or 200 feet of boom.
C. An electronic boom angle indicator shall be provided on al all hydraulic cranes exceeding
15 tons rated capacity or a 60 feet boom length.
7.1 CRANE CERTIFICATE OF INSPECTION AND LOAD TEST
A. All cranes shall have a current annual certificate of inspection and a current quadrennial
certificate of inspection and proofload test located in the crane, issued by a crane
surveyor licensed and accredited by the California Division of Occupational Safety and
Health Administration (Cal-OSHA).
B. All cranes that perform lifts with the jib attachment on Snyder Langston projects shall
have a current certification of inspection stating that the jib has been proofload tested
prior to conducting any lifts.
C. Projects located outside of California, no crane shall be operated or assembled prior to
providing proof certification and inspection consistent with the applicable Federal and
State requirements.
8.1 LOAD RATING CHARTS
A. A durable load chart with clearly legible letters and figures provided by the crane
manufacturer or a certified agent that is experienced and familiar with the characteristics
of the crane equipment shall be securely fixed (where the manufacturer’s load chart is
provided in a binder or other book form, the chart shall be located in the operator’s cab)
to the crane in a location clearly visible to the operator or within reach of the operator
while at the control station.
9.1 CRANE SURVEY PROCEDURE
A. All cranes rated 14.5 tons or more shall be subject to a safety survey performed by a
qualified third party prior to commencement of work.
B. Notice shall be given to the Snyder Langston Project Superintendent by the subcontractor
72 hours prior to the arrival of crane equipment.

Page 27
Revised: August 5, 1999

C. Pre-Erection Hazard Analysis form shall be completed and submitted to the Snyder
Langston Project Superintendent 24 hours prior to crane arrival.
D. The crane survey shall include the inspection of the crane, certificate of inspection and
testing documentation, accessory equipment to be used on the project, and below-the-
hook lifting devices that will be used for lifts on the project.
E. The crane surveyor shall view the set up of the crane and operation of the crane in order
to evaluate the safe operation and use of the crane equipment.
10.1 CRANE SUSPENDED WORK PLATFORMS
A. The use of a crane or derrick to hoist employees on a personnel platform is prohibited,
except when the erection, use, and dismantling of conventional means of reaching the
worksite, such as a personnel hoist, ladder, stairway, aerial lift, elevating work platform or
scaffold, would be more hazardous or is not possible because of structural design or
worksite conditions.
B. If a crane suspended work platform is used, its use shall be conducted in accordance
with the applicable state and federal regulations
11.1 CRITICAL LIFT PLANS
A. A critical lifts is established where any one of the following conditions are created:
1. Where in the crane’s current configuration at any point during the lift, a gross
load weight exceeds 75% of the capacity of the crane, or 85% of the capacity of the
crane where tilt-up panels are erected.
2. A single lift that two or more cranes are used including tandem lifts and tailing
cranes.
3. Lifts made in close proximity of power lines as defined by the voltage clearance
specifications described above.
4. Lifts involving specialized or unique and complex rigging equipment.
5. Hoisting of suspended work platforms.
6. Static tower crane erection and dismantelment.
7. Making lifts below the ground level where the crane is positioned. Where the
below the ground lift is minimal, a critical lift plan may not be required.
B. A critical lift plan shall be submitted to the Snyder Langston Superintendent and Crane
Surveyor 72 hours prior to the crane’s arrival at the job site.
C. The plan shall be consistent with the criteria set forth in the Snyder Langston Mobile
Crane Safety Manual.

Page 28

You might also like