Maintenance closures

Programme of closures of all the Barrier gates for experiments and testing in accordance with clauses 3 and 4 of the scheme.

The times listed below are given in current local time. The times may vary as a result of a particular experiment or test that the engineers wish to conduct while the river is at their disposal or because of the weather. The closure and re-opening of the gates may commence up to an hour before the times listed below. Very occasionally, closures may be cancelled at short notice for navigational reasons. Please telephone the day before to check.

Day of Week

Date

Approximate time river will be closed

Tuesday 19 August 2008 09.15-11.45
Sunday* 28 September 2008 06.50-16.50
Thursday 16 October 2008 08.15-10.45
Monday 17 November 2008 09.15-11.45
Tuesday 16 December 2008 09.20-11.50
Tuesday 13 January 2009 08.25-10.55
Wednesday 11 February 2009 08.15-10.45
Thursday 12 March 2009 07.55-10.25
Thursday 9 April 2009 07.45-10.15

*Full tidal closure

You can telephone the Thames Barrier Information and Learning Centre the day before a planned closure to check that it is still going ahead as scheduled.
Tel: 020 8305 4188


Additional links: regional information

uk

Anglian | Midlands | North East | North West | South West | Southern | Thames | Wales


Back to top of page

©The Environment Agency 2008
Privacy Policy

Author: Diane Peat | enquiries@environment-agency.gov.uk